In the Preschedule step set the proportion remaining to drill, charge, or mine.

...

Single Record Preschedule

  1. Select an activity from the Activity list.

  2. Expand the record tree to the blast or dig solid.

  3. Set the proportion (or volume) remaining.

  4. Manual Values will be displayed Bold Orange (as per Legend in the Activity panel).

...

Bulk Preschedule

  1. Select an activity from the Activity list.

  2. Expand the record tree to a given level.

  3. Right click > “Set Values to …” option > (amount remaining).

...

Preschedule options

Use the dropdown menu available through the right mouse click to:

  1. Set all values for the selected record to 1.

  2. Set all values for the selected record to 0.

  3. Set all values for the selected record to the proportion specified.

  4. Clear Proportion Values set manually.

  5. Clear Proportion Values set automatically.

  6. Clear Values set for Delays.

...

Graphical Preschedule

  1. Click Edit Graphically button.

  2. In the Reserves Shading field dropdown select “<Proportion Remaining (Activity)>” option.

  3. Select one or more blocks for prescheduling.

  4. Right click > “Specify Remaining Value for Selected Blocks” option > enter new value in a dialog > OK.

...

Automatic Preschedule from Surface

  1. Press Use Surface button.

  2. In the Preschedule with Surface dialog choose Surface to use for prescheduling, min/max Thresholds, Records to check and Activities to preschedule .

...

Clearing Preschedule Data

...

Review the preschedule data, you may find that some blocks have volume but no tonnes, or vice versa.

  1. Check the blocks affected in Rapid Reserver:

    1. Navigate to Rapid Reserver > Designer tab > select the block from APS Preschedule error message description > check its tonnes and volume in the Reserves tab at the bottom of the screen > most likely you will see the same missing values.

    2. Some blocks can be outside of the Block Model coverage > make sure you are using Block Model Gap Filling function, where default densities (this is essential) and tonnes are assigned (enable “Fill Block Model Gaps' in the Settings step).

    3. If Block Model Gap Filling is used correctly, but the error message in APS Preschedule persists, check your Reserves mappings in the Block Model step > Reservable Model Generator.

      1. Change the volume and tonnes expressions to exclude blocks with Zero density, ie:

        1. volume = N("density") > 0 ? N("size (X)")*N("size(Y)")*N("size(Z)") : 0, or N("size (X)")*N("size(Y)")*N("size(Z)");

        2. tonnes = N("density") > 0 ? N("size (X)")*N("size(Y)")*N("size(Z)")*N("density") : 0, or N("density") > 0 ? N("size (X)")*N("size(Y)")*N("size(Z)")*N("density") : N("size (X)")*N("size(Y)")*N("size(Z)")*2.5 (density).

      2. Regenerate your Reserves Model and review the changes.

...