For example, the schedule transaction "Pit to Crusher" can be split into "80% direct tip, 20% rehandle" with a different fleet for each movement.
Waste parcels will have one Source and one Final Destination using the Pit Fleet (combined).
Stockpile material will have one Source and one Final Destination using the Rehandle Fleet.
Ore movement can have two steps:
From the Pit to the Stockpile using the Pit Fleet @1.0 means 100% of material follows this step;
From the Stockpile to the Crusher using the Rehandle Fleet.
The available destinations for these steps are the same as those input in the Destination rules.
...
Each rule lists the Steps for transactions that match its filter criteria:
...