Conformance Check (Using Exported Surfaces)

...

3. Check the Parcel Mappings in the Parcel Mappings field  to field to ensure they are correct. Specifically make sure the Volumes and Tonnes fields are correctly mapped or calculated. Fix as required.

...

  1. Navigate to Choose Data Sources task in Setup and Re-Import your updated .invModel overwriting your existing blocks. Check the date, time and file size of the imported file to ensure the correct file is selected.

  2. Re-check the parcel mappings in the Setup tab task Map Fields and make sure they are correct especially with regards to Volume and Tonnes fields for each phase.

  3. As an optional step check some random blocks or phase volumes, tonnes and grades with the corresponding location in Rapid Reserver.

  4. After completing the Setup Task Reserves, go to the Haul Infinity tab, Scheduler menu and Import import the blocks from the scheduler. Ensure all the blocks are connected to the network.

  5. Return to ATS and run all Setup tab tasks by pressing double play icon and run the Schedule tab scenario again.

  6. Assuming scenario run has completed and excluding any variations you may have encountered, Export updated Stage Plans for All Periods.

  7. Unzip new Stage Plans ready for next step.

...

If you still experience significant differences in your values after following the above steps please contact Alastri support via alastrisupport@micromine.com.

...