Solution: It is now possible to model up to 10 user-defined wall activities on a section of the wall. To use this functionality, the “Model Wall Panels” feature must be enabled, as well as enabling the creation of wall panels within the RR project. More information regarding Wall Activities can be found here /wiki/spaces/212AD/pages/30938661 .

...

Improvement in

...

Presplit Drill Hole Visualisations

Problem: When PreplistDrilling PresplitDrilling and PresplitChargingweres PresplitCharging are enabled, it wasn't easy to visually distinguish the drilled and blasted states.

...

Option

Description

Show Undrilled Holes

If enabled, when presplit drilling begins on a pattern, empty production holes won’t be laid out on the remaining area.

Show Blasted Holes

If enabled, once presplit holes have been fired, the blasted holes will remain present on the pattern until blasting of the production holes occurs.

Stockpiles - Force

...

New Decisions

Problem: When stockpiles in a mutex set have a build target type, the “Hours between stockpile decision” input could cause loaders to remain on stockpiles that do not align with the new build targets. The result would cause a volatile grade curve for the stockpile build.

Solution: Once the state of the stockpile build changes, override the “Hours between stockpile decision” option and force Agents to make a new decision. This functionality can be enabled in the Stockpile Build Settings.

Stockpiles - Delays

...

Between Reclaiming and Building

Problem: When a stockpile in a mutex set finishes reclaiming, the software can start dumping there immediately. In some cases, this is not practical as the tip head of the stockpile needs to be reestablished.

Solution: Before a stockpile changes state, a delay specified in hours can be enforced. This functionality can be enabled in the Stockpile Build Settings.

Period Filter for Animation Export

Problem: When exporting the animation, it was not possible to filter the export by period. The whole animation would need to be exported and then filtered in external editing software.

Solution: Include a period filter in the Animation export configuration, allowing users to specify which periods they want to export the animation for.

...

Properties Grid available in Destinations tab

...