Tactical Scheduler - Improvements

Long Term Stockpiles

Problem: It was not possible to store materials that were not required right away, e.g. low grade material, in a long term stockpile location that you may or may not end up reclaimingusing.

Solution: ATS Alastri Tactical Scheduler now has the ability to map a phase as a Long Term Stockpile. This has the benefit of allowing users to configure their setup to dump a certain grade of material at a location, that also has the option of reclaiming from, should the need arise. A simple, intuitive and straight forward workflow has been added to Alastri Tactical Scheduler which allows users to achieve this goal.

After configuring phases in Rapid Reserver and adding levels to a Long Term Stockpile table in Create Tables setup task, an option will show in the Destination Table field to map the Phase to the Long Term Stockpile table.

...

A new setup task, Long Term Stockpiles, has also been added. This setup task allows for the configuration of options such as setting the parcel to be reclaimed from the Long Term Stockpile.

...

Import/Export Priority Incentive Block Sequence

Problem: Priority Incentive block sequences could not be exported from one project and imported into another.

Solution: Priority Incentive block sequences can now be imported and exported between projects.

...

Phase Adjacencies Enhancements

Problem: It was not possible to apply dependencies across stages. This may be desirable for projects containing either nested stages, or where there is a stage above another stage (but not nested inside it.

...

Further, in the Between Benches and Drilling steps, there is an extra column called “Adjacent Phase Expand Distance”. If you specify a number here, it will be used as the expand distance for between phases. If you hit the X, it will instead use the value in expand column.

...

Chrono Report - Calculated Expression Enhancements

Problem: When referencing table rows using Calculated Expressions in Chrono reports, if part of the name of the row being referenced changed for any reason (e.g. something had to be renamed at a certain level), this would break the Calculated Expressions, and all references to the row would need to be fixed.

Solution: It is now possible to use relative paths when using Calculated Expressions. This eliminates the need to update any rows being referenced when changes occur.

...

Agent Priorities

Problem: If two Agents select the same block and parcel, however, only one Agent is allowed on a solid, currently, the only way to prioritise which Agent takes precedence is via the Agents list itself.

Solution: It is now possible to order Agents by priority in the Agent Priorities section of the Calendar.

...

Drill and Loader Labels in Animation Viewport

It is now possible to hide/show labels for Drills and Loaders individually in the Animation Viewport.

...

Calendar Incentives/Constraints

It is now possible to configure how the category rows for some Incentives and Constraints are showing in the Calendar. Previously there was no control over how these were displayed, and they would always appear as grouped. Now, for the Attractiveness Incentive and Sources/Drill Sources/Bench Advance/Agent Assignments Constraints, it is possible to display these in a flat format.

...

Export/Import Calendar Dashboard Templates

It is now possible to export and import calendar dashboard templates. This can be useful when copying dashboards from one project to another.

...

Goal Seek Scripting Enhancements

New options have been added to GoalSeekContext:

...

Production Scheduler - Improvements

New Task Panel Views

The APS task panel has new options for viewing the all tasks. As well as the original way of viewing all Reserves in the gantt style layout, it is now possible to select Agents - Default with Delays and Agents - Default without Delays. The two new options display a list of Agents and each of their tasks across all periods with or without delays. There is also new scripting functionality which allows users to configure the tasks in a custom way.

...