Extension Data Sources & Parameters
Just like APS, it is now possible to read external data sources into ATS in a clean and easy manner. A dedicated Setup step, Extension Parameters, can be enabled where users can load in required data into ATS. Previously, this process either involved hardcoding file paths in the scripts or loading in file paths as through the Refinements step. Once data has been loaded into the project, the data remains embedded in the project file until the data source is refreshed.
Dependencies
Several new Auto Rule Types have been created in the On Bench Dependency step to help speed up the schedule run time. Auto Rule Types from previous versions are still present. The table below outlines each of the Auto Rule Types now available in ATS.
...
It is now possible to create custom exports from within ATS. These reports are required when data can’t be extracted from the schedule using traditional export methods. As the export is created through scripts, it is possible to push data directly through to an external system provided there is a suitable means to do so.
Spatial Conformetrics
Rapid Reserver
Bench Preconditioning
Infrastructure
Haul Infinity
Rapid Reserver
Bench Preconditioning Workflow
The workflow for Bench Preconditioning has been refactored so that it works better with wall segments. The process has now been broken up into two individual steps, Bench Preconditioning and Bench Depletion.
Bench Preconditioning
The Bench Preconditioning step is designed to work on the original Phase solid, not the depleted Phase solid. Material can either be sent to the bench above or below. This can be helpful when there are parts of the bench that need to be drilled with the bench below such as sump shots and contour areas.
...
Info |
---|
When material is sent to another bench, that material will become part of that bench. This means when the parent bench is mined, the additional material will also be mined. |
Bench Depletion
The Bench Depletion deals with material that exists within the flitches of the depleted phase solid. Similar to Bench Preconditioning, material within a flitch can be sent to the flitch above and below. This functionality can be useful when remnant material will be mined with the flitch below.
...
Infrastructure Module
It is now possible to model infrastructure sites and what impact they have on the mining schedule. Heritage, bores, environmental are just some of the Infrastructure sites which can be modelled. This functionality is an external module and therefore may not be accessible to all users. Please send any queries about the module to support@alastri.com.au.
Haul Infinity
-
Spatial Conformetrics
-
Bug Fixes