See below recommended steps to resolve poor digger utilisation in a period.

...

If the schedule has these overflow issues, resolve them first:

Check 1: Schedule > Calendar > Loaders

...

If the dig rate looks wrong, check and update your Haul Infinity inputs.

Check 4: (Loaders as Agents) Schedule > Calendar > Agents > Agent Rates

...

  • Move the animation to when the digger shuts down.

  • If the digger is halfway through a block, select that block. If it just finishes a block, select the next logical block that it should mine.

  • Right click > "Show Dependencies and Traces" > filter the Agents column by the digger name.

  • Read through the activity as per TS. Trace Report section Report section to find out why the digger shut down.

...