See below recommended steps to resolve poor digger utilisation in a period.
...
If the schedule has these overflow issues, resolve them first:
See TS. Overflow Warning.
Check 1: Schedule > Calendar > Loaders
...
If the dig rate looks wrong, check and update your Haul Infinity inputs.
Check 4: (Loaders as Agents) Schedule > Calendar > Agents > Agent Rates
...
Move the animation to when the digger shuts down.
If the digger is halfway through a block, select that block. If it just finishes a block, select the next logical block that it should mine.
Right click > "Show Dependencies and Traces" > filter the Agents column by the digger name.
Read through the activity as per TS. Trace Report section Report section to find out why the digger shut down.
...