The Parcel Subsets allow step allows groups like “ore” to be created and managed in a single place, so that any changes here propagate to all other references in the Setup.

Table of Contents
Info

Note that what is defined as “ore” may change from plan to plan, so the user should always double check the subsets are correct with each new planning cycle.

...

Grouping up parcels (into ore and waste, for example) allows the user to reference these names later in the Setup. This makes it easy to manage any changes to material type names, or to include new material types into the existing “ore” and “waste” groups.

To create a Normal Subset:

  1. Select the “Mining” activity from the Activity list.

  2. Use the plus icon to add a new subset.

  3. Select the Name field and rename to “Ore”.

  4. In the Parcel list, tick all ore parcels.

...

Hold <SHIFT> and select parcels and <Ctrl+V> to paste values into a range of parcels

Important Note

Mutex subset specified in this step will be used in the Final Configuration step to define Haulage Materials.

...

Warning

Avoid having “Unassigned” as a group for parcels, because it will lead to an error “The following material types are missing from the Haul Infinity Project (Unassigned)” when you run the Final Configuration step.

...

Tip

Assign groups according to materials specified in Haul Infinity > Cycle Times > Materials step.

...