The Work Schedule step represents a collection of recurring operational delays. Work schedules can be created for various mining operational groups, such as Production and Development, to capture distinctive delay schedules.
...
Info |
---|
The <Full Time> work schedule is a default schedule and can’t be edited. |
...
Section | Description |
---|---|
Recurring Delay | Untick if the delay is a singular occurrence |
Time of Day | Set the start time of the delay as well as the duration |
Recurrence Setup | Daily - specify the recurrence at a daily granularity. Weekly - specify the recurrence at a Weekly granularity. Monthly - specify the recurrence at a Monthly granularity. Yearly - specify the recurrence at a Yearly granularity. |
Recurrence Range | The overarching duration in which the delay will be applied. Start date - specify the start date from which the delay will take effect. End Date:
|
...