An Activity Sequences step can be used to set logical dependencies between activities, i.e., you can’t mine a blast until it has been drilled and blasted. These can be constrained to a particular record set, defined by the user.

...

Info

Subsets created in the Setup tab > Record Subsetsstep are available to be used here.

Column

Description

Records

Select record subsets to apply the following dependency to

Successor

The activity to follow the predecessor activity

Predecessor

The activity to be completed before the successor activity

Delay (h)

A delay, specified in hours, which will be applied to the successor activity once the predecessor activity has been completed

To add an Activity Sequence:

...

Info

Activity Sequences can be added through scripts. These entries in the table will appear in bold blue and can’t be edited.

...