With specified wall control, Blast Shapes Generator will easier create trim shots based on presplit location and length.

...

Wall Panel Activities setup- Alastri Production Scheduler

Production Mode Features

Activities to perform on wall panels can be defined in the Wall Panels tab located down the bottom of the Production Mode Features step (Features Settings panel). Alastri Production Schedulersupports up to 10 different activities and once defined in the project, behave like all other activities within the app.

...

In the Setup > Agents, review equipment assignment, and select the colour and Agent icon you wish to use for your equipment.

...

Wall Control Activities scheduling - Alastri Production Scheduler

Calendar tab

In the Calendar, select the Loader which will conduct the Wall Scaling activity and update the Mining Rate for the rates in metres per hour. Repeat the steps for the Cable Bolting and Presplit Drilling agents.

...

Gantt

In the Gantt, add/edit a sequence for the loader used to conduct Wall Scaling as per normal and schedule the batter blocks to be mined by the specified loader. Repeat the process for the Cable Bolting and Presplit Drilling agents.

...

 

Animations

Run your schedule and visually check the activities are being carried out before adjusting to suit.

...