Below in this section you’ll find a general overview of the Schedule tab with a brief description of all its components.

Table of Contents

Overview

A general overview of the Schedule tab for a a sample project.

...

Description of the Schedule tab's components see below:

Scenarios Panel

The Scenarios panel is located at the top of the Schedule tab.

...

To change the items displayed in the scenarios area, click on the dropdown list on the right of the panel and select the required one.

...

Tabs

The Schedule tab contains five additional tabs, with different functionality and work viewports. A detailed description of each of them is given below.

...

Calendar tab

The Calendar tab is a calendar plan for the open pit mining, arranged by production periods, mine components, equipment used, and applicable constraints and parameters.

The main area of the Calendar tab is the Dashboard.

Dashboard

Alastri Tactical Scheduler Schedule tab dashboard consists of two main sections:

...

Child pages (Children Display)

Animation tab

The Animation tab provides the user with a graphical representation of the activities performed by periods, as well as the ability to select data to display and set priority incentives. Detailed information about the Animation tab and its panels and fields see here.

Period Plots tab

The Period Plots tab is used to present graphical plots of entire benches or lifts.

...

If Show Legends is checked in the Plot Settings window, you will see a legend of color assignments by period on the right side of the viewport.

Trace tab

The Trace Report (Schedule tab > Trace tab) records decisions made when an Agent evaluates a source block. This provides a useful tool for users to understand why a block was mined (or not) at a particular point in time.

...

More information about Trace Reports see here.

Reporting tab

The Reporting tab is displayed within the context of a given project and enables you to generate any standard or custom report currently available for the project. In this tab you can generate a single report or multiple different reports simultaneously for the project. Once the generation of a report has completed, you may export and download the report in all its available formats.

...

Detailed information on the Reporting tab components, fields and sub-tabs see here.