In the Settings section, you may set units of measurement, options and thresholds to use in the project, as well as hatch patterns and labels.
Enter all global settings to change the behaviour of the project.
...
Label | Reference |
---|---|
Production Start | The name of the surface which represents the production start surface. |
Production End | The name of the surface which represents the production end surface. |
Scheudle Schedule Start | The name of the surface which represents the schedule start surface. |
Schedule End | The name of the surface which represents the schedule end surface. |
...
Label | Reference |
---|---|
Plan Compliance (In Plan / Scheduled) | The name of the report field which reports in plan solids over scheduled solids. |
Plance Plan Compliance (Compliant / Scheduled) | The name of the report field which reports complaint solids over scheduled solids |
Plan Performance (Production / Scheduled) | The name of the reprot report field whcih which reports production solids over scheduled solids. |
...