In the Preschedule step set the proportion remaining to drill, charge, or mine.
...
See the Colors Legend in the bottom left-hand corner of the Preschedule step, which helps understand the meaning of the text colors.
...
Prescheduling
See different options of prescheduling below.
...
Select an activity from the Activity list.
Expand the record tree to the blast or dig solid.
Set the proportion (or volume) remaining.
Manual Values will be displayed Bold Orange (as per Legend in the Activity panel).
...