In the Preschedule step set the proportion remaining to drill, charge, or mine.
...
Select an activity from the Activity list.
Expand the record tree to the blast or dig solid.
Set the proportion (or volume) remaining.
Manual Values will be displayed Bold Orange (as per Legend in the Activity panel).
...
Press Use Surface button.
In the Preschedule with Surface dialog choose Surface to use for prescheduling, min/max Thresholds, Records to check and Activities to preschedule .
...
Clearing Preschedule Data
To clear all manual or automatic prescheduled data, right-click on an activity in the Activity panel and select “Clear Preschedule Data for <Activity>”. All the Preschedule data will be removed and records color return to standard.
...
Notes
Info |
---|
Blocks set for mining as 0 remaining, will appear in graphics with 0 tonnes and 0 bcm. To remove completely use the Record Removal step. |
...