The Trace Report records decisions made when an Agent evaluates a source block. This provides a useful tool for users to understand why a block was mined (or not) at a particular point in time.

Exclusions

Disabled Agents

If an Agent is completely disabled from making decisions (for instance, it has no capacity), then it records nothing in the Trace Report.

Info

If an Agent is completely missing from the Trace Report, check Calendar > Loaders > Direction Utilisation is greater than zero.

Dump Dependencies

In the case where dumps are blocked by dependencies, the Trace Report will show "No Available Destinations" with no further information.

Info

If the Trace Report shows "No Available Destinations" with no other messages, it may be that all dumps are blocked by dependencies.

Example Usage

Resolve an instance where a pit or block is not being mined.

  1. Navigate to the Animation tab.
  2. Drag the animation slider forward to view the mining sequence.
  3. Observe that a block is not mined/drilled at the desired time.
  4. Left click to select the block.
  5. Right click and select "Dependencies and Traces".
  6. Check the Dependency list (top) for unsatisfied dependencies.
  7. Check the Traces list (bottom) for schedule messages.

Image Removed

Trace messages for R9400 in period 12.

Resolve an instance where a stockpile is not being mined:

  1. Navigate to the Trace tab.
  2. Filter the 'Full Name' field and type 'Stockpiles'.
  3. Select the stockpile to inspect.
  4. Read the Traces list for scheduling messages.

Image Removed

Trace messages for stockpile ROM1_1 in period 3.

Info

Note that stockpiles only appear in the Trace Report when scheduling in Truck Constrained mode.

If a stockpile is not reclaiming in Optimised Products mode, review the TS. Спецификации на продукт.

...

В отчете о трассировке (Schedule > вкладка Trace) представлены решения, принятые при оценки агентом исходного блока. Это дает пользователям возможность понять цели разработки блока (или не разработки) в определенный момент времени.

Table of Contents

Исключения

Отключенные агенты

Агенты, полностью отключенные от возможности принимать решения (например, из-за отсутствия вместимости), не вносят никакие записи в отчет о трассировке.

Info

При полном отсутсвии агента в отчете о трассировке, убедитесь, что значение прямого использования в Calendar > Loaders > Direct Utilisation (Календарь > Погрузчики > Прямое использование) больше нуля.

Зависимости для отвала

В случае блокировки отвалов зависимостями, в отчете о трассировке отобразится сообщение «No Available Destinations» (Нет доступных мест назначения) без дополнительной информации.

Info

Вывод в отчете о трассировке только одного сообщения «No Available Destinations» (Нет доступных мест назначения) может означать, что зависимости заблокировали все отвалы.

Пример использования

Пример решения случая отсутствия разработки карьера или блока.

  1. Перейдите во вкладку Animation.
  2. Для просмотра последовательности разработки, перетащите ползунок анимации вперед.
  3. Обратите внимание на блок, разработка/бурение которого не выполняется в требуемое время.
  4. Выберите блок, щелкнув по нему левой кнопкой мыши.
  5. Щелкните правой кнопкой и выберите из раскрывающегося списка «Show Dependencies and Traces» (Показать зависимости и трассировки).
  6. Проверьте список зависимостей (сверху) на наличие невыполненных.
  7. Просмотрите сообщения по планированию в списке трассировок (снизу).

Image Added

Сообщения о трассировке погрузчика R9400 в период 12

Пример решения случая отсутствия разработки насыпи.

  1. Перейдите во вкладку Trace.
  2. Выберите фильтр столбца Full Name (Полное имя) и введите «Stockpiles» (Насыпи).
  3. Выберите насыпь, которую Вы хотите рассмотреть.
  4. Просмотрите сообщения по планированию в списке трассировок.

Image Added

Сообщения о трассировке для насыпи ROM1_1 в периоде 3


Info

Обратите внимание, что данные по насыпям будут отображены в отчете о трассировке только, если планирование выполняется в режиме Truck Constrained (Ограничения по самосвалам).

При отсутствии информации по забору материалов из насыпи в режиме оптимизации продуктов (Optimise Products), см. TS. Спецификации на продукт.

Сообщения о планировании

Actions

MessageNotes
Block created, and added to ASL
.
Dependencies are satisfied; block is available
.
Block loaded into ASL at the start of the period
.
Dependencies are satisfied; block is available
.
Selected block (it was ranked #1)Block ranking based on incentives
.
Removed <AMOUNT> quantity from block
.
Block was mined/drilled
.
Agent cannot fully complete block, as it is near its production limit
.
Block was only partially mined/drilled
.
There is no remaining volume in the block
.
Specific parcel is completely mined/drilled
.
Block is completed, and removed from ASL
.
All parcels are completely mined/drilled
.

Summaries

MessageNotes
No available destinations for block
.

This is a summary message. Read up the list to see the actual issues

.

Waiting for mining block to be released
.
This is a summary message. Read up the list to see the actual issues
.
Unable to completely extract block
.
This is a summary message. Read up the list to see the actual issues
.

Interruptions

TypeMessageNext Steps
DependencyWaiting for mining block to be released by dependencies.Setup > Dependencies > review dependency settings.
DependencyHit a proximity constraint <PROXIMITY> - so cannot choose block.

Drills:

Setup > Dependencies > Drilling > Mining Standoff Distance.

Diggers:

Setup > Dependencies > Between Benches > Max Agents on Block.

DependencyBlasting Delay holding up mining of block.

Setup > Dependencies > Drilling > Blasting Delay.

Setup > Refinements > Custom blast delay inputs (if any).

AgentAgent cannot operate on the block.

Drills:

Setup > Drills > Hole Types > review allowed hole types.

Calendar > Drills > check penetration rate greater than zero.

Diggers:

Calendar > Agents > check that Agent capacity is greater than zero.

Calendar > Incentives > review Maximum/Minimum mining grades.

IncentiveBlocked by priority incentive <PRIORITY>.Animation > Priority Incentives > review blockers in the named priority list.
Destination LogicCould not find applicable destination rule.Setup > Destination Logic > review destination logic.
ConstraintConstraint <CONSTRAINT> prevented sending to <DESTINATION>.Calendar > Constraints > review constraint limit.
CapacityThere is no remaining volume in destination <DESTINATION>.

Setup > Waste Dumps > dump capacity.Capacity

Calendar > Dumps > capacity limit.

Haul InfinityIgnored destination due to no travel time available <DESTINATION>

Haul Infinity > Network > invalid cycle time.

This may be due to no route available, dynamic haulage stage, and/or rimpull/retard curves on the truck.

EquipmentConstraint (Equipment - Step Rule <RULE>) prevented sending to <DESTINATION>.

This message indicates that trucks were exhausted in one of the fleets.

  • Setup > Step Logic > review the fleets used in this movement.
  • Setup > Fleets > see what diggers and trucks are assigned.
  • Calendar > Loaders | Trucks | Fleets > find the exhausted equipment.

This message usually results from over-assigning ROM loaders on ex-pit movement, or from exhausting the available rehandle trucks.

EquipmentBlocked due to exhaustion of available equipment.Calendar > Fleets > check number of units available in fleet.