Функция приоритетных предпочтений Priority Incentive позволяет использовать два очень мощных средства контроля над расписанием:
- The user can specify a preferred block-by-block mining/drilling sequence for any agent at any point in the schedule. (Sequencing)
- The user can specify that certain blocks cannot be mined between certain dates by certain agents. (Deferring)
Practically what this means is that the user can let ATS choose blocks automatically, then choose an exact sequence for ATS to follow for a time, and then release control back to ATS. The user can have different sequences specified for different agents, meaning that each agent can follow a different sequence.
The Priority Incentive also allows users to nominate specific blocks that cannot be mined or drilled for a duration of time. This is also a method of controlling the sequence, but allows to user to tell ATS what NOT to do, rather than what to do. The user can specify these blocks graphically, and individual blocks can be disabled and enabled over the course of the schedule.
Table of Contents |
---|
Creating a Priority Incentive
...
- Пользователь может указывать предпочтительную поблочную последовательность добычи/бурения для любого агента в любой точке расписания (Sequencing/Очередность).
- Пользователь может указать, что некоторые блоки не могут быть разработаны между определенными датами определенными агентами (Deferring/Отсрочка)
Фактически это означает, что пользователь разрешает ATS выбирать блоки автоматически, затем он вручную назначает точную последовательность, которой ATS будет следовать в течение некоторого времени, а далее передает управление обратно ATS. Пользователь может указывать разные последовательности для разных агентов, что означает, что каждый агент может придерживаться своей последовательности.
Функция приоритетных предпочтений также дает пользователям возможность назначать определенные блоки, которые нельзя разрабатывать или бурить в течение определенного периода времени. Это также позволяет управлять последовательностью, но наоборот, когда пользователь отправляет в ATS команду, что НЕ ДЕЛАТЬ, а не что ДЕЛАТЬ. Пользователь может представлять эти блоки графически, а отдельные блоки можно отключать и включать в ходе расписания.
Table of Contents |
---|
Создание приоритетного предпочтения
Приоритетные предпочтения можно создать в шаге настройки Incentives.
Setup > Incentives > Add Incentive > "Priority"
The user can choose a name for the incentive, and specify to which agents the incentive applies.
Info |
---|
|
Once finished configuring the incentives, complete the setup.
Priority Incentives Control Panel
Upon completing setup, go to the Animation tab, and there is a new panel hidden on the left
Schedule > Animation tab > Priority Incentives panel location
Open the panel by clicking on it.
- Use the pin icon to lock the panel in place (1).
- At the top of the panel is a listing of each Priority Incentive created by the user (2).
- At the bottom of the panel is a list of sets (Sequence + Blockers), which are displayed as times (3). The time displayed is the time during the schedule when that set becomes active.
- The four buttons, from left to right, allow the user to create a New set (4), Edit an existing set (5), change the Time of a set (6) and Remove a set (7), respectively.
Priority Incentives panel elements
...
Пользователь может выбрать имя для предпочтения и указать, к каким агентам оно должно применяться.
Info |
---|
|
По окончании настройки предпочтений, завершите настройку.
Панель управления Priority Incentives
По завершении настройки, перейдите во вкладку Animation и найдите скрытую панель слева.
Schedule > вкладка Animation tab > расположение панели Priority Incentives
Раскройте панель, щелкнув по ней.
- Закрепите панель на месте нажатием на значок булавки (1).
- В верхней части панели приведен список всех созданных пользователем приоритетных предпочтений (2).
- В нижней части панели находится список наборов (последовательность + блокатор), отображаемых в виде времени (3). Отображаемое время — это время в расписании, когда этот набор становится активным.
- Четыре кнопки слева направо дают используются для создания нового набора (4), редактирования существующего (5), изменения времени набора (6) и удаления его (7) соответственно.
Элементы панели Priority Incentives
Добавление набора
To add a set, adjust the animation slider (at the bottom of the Animation window) to the time when you want to insert the new set, and press the blue plus icon. It is not possible to add more than one set a the same time, as this would not make sense. When the Animation time is changed, the orange indicator will move to indicate where a new Set would be inserted.
...