Haul Infinity calculates the path-finding, loader rate and truck rate for each haul in the schedule. ATS uses this to deplete equipment hours for each transaction. 

Table of Contents

Parameters

Validate inputs in Haul Infinity > Setup > Parameters. 

...

The parameters table holds cycle time inputs for every combination of loader, truck, and material.

...

Display

In the top left of the parameters table, data can be set to "Iterate" or "Group". 

  • Iterate: update each selected item individually.
  • Group: update all selected items as a group.

...

Selection

When items are selected from the Trucks, Loaders and Materials list, they are added into the Parameters table.

  • Control click to select multiple items.
  • Shift click to select a list of items.

...

Cycle Time Calculations

Haul Infinity calculates cycle times from first principles using the payloads, swing times, and in-cycle delays. 

Loader Payload Calculation

  1. Enter the bucket payload and volume limit.
  2. Haul Infinity calculates the utilised bucket payload.

...

Truck Payload Calculation

  1. Enter the truck tray payload and volume limit.
  2. Haul Infinity calculates the utilised tray payload.

Loading Calculation

  1. Enter the truck filling type:
    1. FullBuckets → less swings to fill the tray, some trucks light-loaded.
    2. FullTrucks → more swings to fill the tray, last bucket light-loaded.
    3. Theoretical → allow the digger to make "half a swing".
  2. Enter the loader cycle time (time to load one bucket).
  3. Enter the loader first pass delay (time to switch between trucks).
  4. Haul Infinity calculates the corresponding load times. 

...

Overrides

The Overrides section can be used to bypass the cycle time calculations. 

...

Make sure to override both Loader Load Time and Truck Load Time to capture the correct truck and loader rates. 

...

Other Inputs

Enter the following inputs:

...