Constraints (Ограничения)

В Setup > Constraints: add constraints to control blast stocks limits, drilling meters by pit or bench, and drill unit assignment by area. 

  • Constrain stocks blasted in the period with a Standard Constraint on drill volume. 
  • Constrain number of each drill type by pit or bench with an Agent Assignment Constraint.
  • Constrain drill quantities by pit or bench with a DrillSource Constraint.

Image Removed

Add constraints in the Constraints step

Schedule Calendar

...

добавьте ограничения для управления пределами для взрывных запасов, расстояний бурения скважин по карьеру или по уступу, а также для назначения буровых установок по участкам.

  • Ограничьте взорванные в период запасы с помощью стандартного ограничения по объему бурения (StandardDrill).
  • Ограничьте количество буровых установок каждого типа по карьеру или по уступу с помощью ограничения назначения агента (AgentAssignment).
  • Ограничьте объемы буровых работ по карьеру или по уступу с помощью ограничения источника бурения (DrillSource).

Image Added

Добавление ограничений в шаге Constraints

Календарь расписания

Бурения

Enter the total number of drills and time usage by period. 

...

Info

Priority Incentives are defined in Setup > Incentives. The manual sequence is entered in Schedule > Animation > Priority Incentives

...

Ограничения

Enter the values by period in each constraint. 

...

Constraints fields in the Calendar tab

Priority Sequencing

...

Последовательность приоритетов

Перейдите во вкладку анимации Animation и найдите панель Priority Incentives, расположенную в верхнем левом углу экрана. Сначала отредактируйте приоритетные предпочтения для каждого карьера и предварительно назначьте последовательность бурения для всего карьера. Таким образом, при каждом назначении буровых работ для данного карьера в Calendar > Constraints > Drill Assignments, it will pick up the sequence where the last drill left off, будет выбрана последовательность, на которой закончилось последнее бурение

Priority Incentives in the Панель Priority Incentives во вкладке Animation tab

To enter priority sequences:

  • Use the slider below the viewport to view the nominated sequence.
  • Blocks can be inserted in the sequence by moving the slider to the insertion point and adding blocks with the Draw Sequence tool.
  • Blocks can be removed from the sequence by selecting them in the list and pressing the remove Image Removed icon. 

To ban blocks from drilling or mining:

  • Click the Draw Blockers tool and select blocks to ban from the all activities. 
  • Blocks can be unbanned by selectin them in the list and pressing the remove Image Removed icon. 

Image Removed

Block Sequencer overview

...

Note that each Priority Incentive may have more than one Priority Sequence listed under it. Each Priority Sequence persists from its starting time until the starting time of the next Priority Sequence, at which point the first sequence is completely flushed. 

...

Для ввода последовательности приоритетов

  • Для просмотра назначенной последовательности используйте ползунок, расположенный под областью просмотра.
  • Для добавления блоков в последовательность переместите ползунок в желаемую точку вставки и добавьте блок с помощью инструмента рисования последовательности Draw Sequence .
  • Для удаления блоков из последовательности выберите их их списка и нажмите значок удаления Image Added

Для запрета бурения или разработки блоков:

  • Нажмите на инструмент Draw Blockers и выберите блоки для исключения их из всех действий
  • Блоки можно обратно разблокировать, выбрав их из списка и нажав значок удаления Image Added

Image Added

Общее представление окна Block Sequencer

Note

Обратите внимание, что под каждым приоритетным предпочтением может быть больше одной последовательности приоритетов. Каждая последовательность сохраняется с момента ее начала до времени начала следующей, после чего первая последовательность полностью очищается.

Например, если Вы блокируете блоки в момент времени Х, а затем добавляете новую последовательность приоритетов в момент времени Y без заблокированных блоков, то эти блоки будут считаться разблокированными и доступными для бурения/разработки.