How do they work and what numbers do I enter.
Why do I need an Agent Rate when I already have a Loader Rate?
The loader rate is not known until after the period is run:
The Loader Rate is dependent on truck payload and cycle time.
The truck and cycle time are dependent on the destination.
In Optimised Products mode, trucks and destinations are not assigned until the end of the period.
Therefore, in order to run one period, a target is required.
The Agent will mine a certain amount of tonnes in a period.
The Loader has a fixed amount of hours.
Agent Rate = Agent target / Loader hours.
When using Loaders as Agents, the user may enter an Agent Rate in each period, and ATS will automatically scale that to an appropriate target for the period duration. This saves the user from В этом разделе объяснены принципы работы скорости агента, а также рекомендации по вводу числовых данных.
Зачем мне нужна скорость агента, если у меня уже есть скорость погрузчика?
Скорость погрузчика неизвестна до тех пор, пока не будет запущен период:
Скорость погрузчика зависит от полезной нагрузки самосвала и времени цикла.
Самосвал и время цикла зависят от пункта назначения.
В режиме оптимизации продуктов грузовики и пункты назначения не назначаются до конца периода.
Следовательно, чтобы запустить один период, требуется цель.
Агент будет разрабатывать определенное количество тонн за период.
Погрузчик имеет фиксированное количество часов работы.
Скорость агента = цель агента / часы погрузчика.
При использовании погрузчиков в качестве агентов пользователь может вводить скорость агента для каждого периода, и ATS автоматически масштабирует ее до соответствующего целевого значения для продолжительности периода.