Update In the Final Configuration step user can update final configuration.
...
Haulage | Configure integration with Haul Infinity |
---|---|
Use | If ticked, automatically imports scheduling blocks into Haul Infinity. |
Assign Joins By Segment Name | If using Ramp locking function in Haul Infinity, check on “Assign Joins by Segment Name” . |
Calculation Timeout (s) | How long APS will wait for Haul Infinity to complete its calculations before giving up and returning control of the program to the user. |
Haulage Materials | Choice of Mutex Parcel Subset for representing payloads in Haul Infinity. Example: 26 material types may only need two payload quantities (ore, waste). |
Destination Fill Sequencing Method | Option to use quickest <TravelTime> or shortest <Distance> in deciding which dump to fill first in the sequence |
Quick Truck | Default truck to use for pathfinding calculations in Haul Infinity. |
Truck Calculations | Automatically allocate instantaneous trucks in each steady state while not changing the ability to think about trucks in the traditional TUM paradigm. | Enable Truck Dispatch|
---|---|---|
Enabling this option means trucks will be assigned based on digger priority | Show TUM Graphs | Shows on the “TUM Trucks” graphs on the Gantt diagram |
Show Instantaneous Graphs | Shows on the “Instantaneous Trucks“ graphs on the Gantt diagram | |
Specify Minimum Agent Operating Rates (Slows Scheduling Speed) | Unticked by default | |
Limit Maximum Trucks by Agent | ||
Limit Materials | Mutex parcel subset to apply to. | |
Time Format | Description | |
Toggles logic to limit maximum amount of trucks by Agent | ||
Limit Maximum Trucks by Rule | Toggles logic to limit maximum amount of trucks by Rule |
Display settings | |
---|---|
Hatch Pattern | Select a pattern from dropdown to outline different settings |
Time Format Large Label | Time format for Scenario time slider. Formatting options can be found here. |
Time Format Small Label | Time format for Scenario time slider. Formatting options can be found here. |
...
Gantt | Description | |
---|---|---|
Do Nothing When No Sequence | Toggles whether a digger obeys the /wiki/spaces/PS1D212AD/pages/2870599230936650 rules when it has no sequence (iei.e. have crib breaks and shift change). |
BlastingDescription | |
---|---|
Blast Exclusion (m) | Blast Exclusion radius. Any Agent working within this radius of a block being blasted will stop for the duration of the blast window |
Optimisation | Inputs to incentivise the Agent to follow requirements | ||
---|---|---|---|
Solver parameters | |||
Solver | LPSolve is the default solver Alastri uses. If your setup has a third party solver integrated, select it here. | ||
Server, User Name, Password | Enter relevant Server, User Name, and Password | ||
Default Movement Cash ($/dt) | Incentive to keep digging (even if no other optimisation input is specified). | ||
Agent Priority Cash ($/dt) ($/dt) | Controls how strictly the diggers adhere to the Agent Priorities in the Calendar. | ||
Destination Order Cash ($/dt) | Reward for honouring the list order of destinations in a destination rule. | ||
Destination Affinity Cash ($/dt) | Reward for continuing to send a reserve block to the same destination (instead of splitting it across stockpiles). | ||
Mutex Fill Order Cash ($/dt) (-1 to disable) | Incentive to fill the largest stockpile in a mutex group (has the effect of minimising turnover time). Enter -1 to disable out-of-order filling entirely. | ||
Stockpile Priority Cash | Incentive to reclaim stockpiles in order, when multiple stockpiles are added to a single Gantt sequence. | ||
Hours between new Stockpile Decisions (-1 to disable) | Time period before a Loader moves to another Stockpile. Reduces the times the optimiser will move a loader between stockpiles if has multiple options availableHours between new Stockpile Decisions (. Enter -1 to disable ) | Time before the Agent evaluates whether to reclaim a new stockpile | function. |
One Loader per Stockpile | When ticked, enforces a maximum of one loader to be active on a stockpile at a time. | ||
Remain on Stockpile Cash ($/tdt) | Incentive for a loader to remain on the stockpile that it is already on. | ||
Disable Simultaneous Build/Reclaim | Will not allow a stockpile to build and reclaim at the same instant in time. | ||
Enable Single Chunk Stockpile AutoTurnover | Change a stockpile from build mode to reclaim mode based on the optimisation. This function only works when the stockpile is not part of a mutex set, there is only one chunk, and the stockpile can be both built and reclaimed. |
Shared Agents | View how another scheduler is utilizing shared agents in a Project |
---|---|
Path | Path to a location shared by both schedulers. |
Refresh Seconds | Refresh time. |
Info |
---|
A new Shared Agent panel will appear on the Gantt and diagram, as well as a new row called Other User“Other User”. |
Exports | |
---|---|
Reports/Chrono | Setup items export to the Chrono reports |
Export Key Column | Enable to export Key column to the Chrono report |
Export Units Column | Enable to export Units column to the Chrono report |
Product Feeds | Setup feed export for input to another schedule |
Split on Period Boundary | Default. APS will export periods as defined by the calendar |
Split on Breaks in Feed | Select this option to allow split on Breaks in Feed |
Hours Between Splits | Export on smaller time periods than those setup in the schedule |
Info |
---|
These exports are for import to another Project using a second site for feed, see PS. Second Site. |
Simultaneous Charging | Controls level of charging that can occur on a blast that is still being drilled |
---|---|
Simultaneous charging will allow the explosive loading to start on a blast pattern before drilling has finished on that pattern. one of two options can be selected. | |
Percentage Buffer (-1 to use Quantity) | The percentage of the pattern to be drilled before loading can commence. Default is 100%, complete drilling before loading can commence. |
Quantity Buffer (length) ( -1 to use Percentage) | The meterage advance of the drilling on the pattern to be drilled before loading can commence. |
Info |
---|
Note: If Charging has been made dependent on Production Drilling in the Activity Sequences, Simultaneous Charging cannot happen. Remove this dependency if Simultaneous Charging is to be used. |
Advanced | |
---|---|
Memory Increase Before Garbage Collect (MB) | Point at which schedule stops to clean up memory. |
Info |
---|
The software appears frozen while the clean up is in process. |