Enter the The Calendar tab consists of two main parts: Dashboard and Calendar itself.
Table of Contents | ||||
---|---|---|---|---|
|
Dashboard
Dashboards allow a user to create custom Calendar layouts. This can be used to organise rows into a concise summary of equipment used, tonnes moved, and grades achieved. More details see here.
Calendar Inputs
Input the necessary planning parameters, such as crusher rates, dig rates, truck numbers, and product grades for the schedule.
Switches
Enter the switch values by period.
Info |
---|
Switches may be used to change destinations and material flow over time. For more information, see PS. Calendar Switches, PS. Destination Rules, PS. Flow ChartChats sections. |
...
Ratios
Enter ratio values by period.
Info |
---|
Ratios may be used to control percentages of product type created in each period. For more information, see PS. Ratio Splitters , Flow Chart and PS. Flow Chats sections. |
...
Calendar ratio values by period.
...
Stockpiles
Enter capacity limits and turnover triggers.
Info |
---|
Use the Delete <Delete> key in Stockpile rows to reset limits and triggers. |
Force Mode
Can force a stockpile into build mode, reclaim mode, or off entirely. This allows the user another level of control over stockpile blending.
Turnover Trigger
Turnover triggers only apply to Blended and Mutex stockpile types.
If a stockpile hits the turnover trigger during the period, it switches from building to reclaiming.
Capacity Limit
Stockpile capacity is set by the Chunk Template in PS. Stockpiles Setupstep.
Chunk Template capacity is the sum of chunks in PS. Stockpile Chunks step.
If the Capacity Limit is set to less than the Total Capacity, then the stockpile will pause building (it will not reclaim).
If the Capacity Limit is set to greater than the Total Capacity, then it has no effect.
...
Stockpile Sets
For mutex stockpile sets, Force Mode can force all stockpiles in a set into build mode or reclaim mode.
To determine which stockpile will be reclaimed next, give it a higher priority in the mutex stockpile set or use -1 to force it to immediately switch to reclaiming the chosen stockpile.
...
...
Info |
---|
To force stockpiles to build in a certain order, run the schedule, scroll across to the period where the stockpile chosen is not the desired one. Change the priority at this period to force the reclaim order. |
Crushers
Enter crusher rates by period.
Info |
---|
Note that calculating the rate as target tonnes over working hours only works if the crusher is constantly fed. If there are gaps in the feed, you are better off combining a maximum rate with a period constraint. |
...
...
Dumps
Optionally enter dump limits in the calendarCalendar. Note that dumps automatically detect their own volume, so manually constraining their capacity is rarely required.
...
Default Rates
Enter default rates for non-mining activities. These are used to put a cool-down timer between when a blast is exposed and when it can be mined in the Mining Mode schedule runs.
...
...
Haulage Flags
Enter haulage flags by period.
...
Agent Priorities
If two agents are assigned to the same block, the agent with a lower priority will stop and wait for the agent with a higher priority.
...
...
Trucks
Enter truck numbers and time usage.
...
Agents
Enter agent rates, number of allowed trucks and maximum instantaneous trucks. Instantaneous trucks will be the maximum allowed trucks at an instance for a particular transaction set.
...
Calendar agent rates.
Trucks
Enter truck numbers and time usage.
...
Calendar truck numbers.
...
Truck Assignments
Set the maximum trucks that can be used by each fleet grouping.
...
...
Optimisation
Enter cash flows and grade targets.
...