Increment offsets may be used to force a minimum or maximum vertical lag between phases.
Info |
---|
Every bench at elevation (E) in the Successor stage is made dependent on the bench at elevation (E+Offset) in the Predecessor stage. Offsets may be positive or negative. |
To add an Increment Offset:
- Press the clipboard icon to add a new rule group.
- Rename the rule group (i.e. mining rules, backfill rules, land-bridge rules).
- Using the tree hierarchy on the right, select the successor record and double click on the predecessor.
- Set the Vertical Offset in metres:
- Negative to keep the successor elevated over the predecessor
- Positive to keep the predecessor elevated over the successor
- Verify the dependencies in the Preview panel.
Example of a 20 metre vertical lag between stages.
...
Настройки, приводимые в шаге Increment offsets (Смещения приращения) могут использоваться для обеспечения минимального или максимального вертикального смещения между фазами.
Info |
---|
Каждый уступа на высотной отметке (E) на этапе Successor (Последующий) становится зависимым от уступа на отметке (E + Offset) на этапе Predecessor (Предшествующий). Смещения могут быть положительными или отрицательными. |
Для добавления смещения приращения
- Нажмите значок папки , чтобы добавить новую группу правил.
- Переименуйте группу правил (например, правила разработки, правила обратной засыпки, правила насыпей).
- Из иерархии древовидной структуры справа выберите последующий этап (Successor) и дважды щелкните по соответствующему предшествующему этапу (Predecessor).
- Установите вертикальное смещение в метрах:
- отрицательное — чтобы последующий этап был выше предшествующего,
- положительное — чтобы предшествующий этап был выше предыдущего.
- Проверьте зависимость на панели предварительного просмотра Preview.
Пример настройки 20-метрового вертикального сдвига между этапами разработки
Поперечный разрез, показывающий влияние вертикальных смещений на разных этапах разработки