How to set up drill scheduling in a production model. 

Introduction

Drill scheduling introduces delays relating to blasted stocks, available real estate, and fleet logistics. 

...

Finished plans may be published as a colour-coded drill plot for issue to 48-hour planners.

Workload

Drill scheduling requires preparing, importing and using data in addition to the existing production schedule workload. 

...

  • Enter drill meters remaining in half-drilled shots.
  • Enter number of drills operating in a pit, stage or bench. 
  • Enter manual drill sequences at the bench level (if required).

Setup Procedure

Step by step guide to set up drill scheduling in a production model. 

Rapid Reserver

In Rapid Reserver, add the blast properties which will affect drilling. 

...

Choose blast properties that are appropriate for your site. 

Blast Tags

Configure the block tags in Rapid Reserver > Designer tab > Display menu.

...

  • Blanks will be assigned default blast parameters (ie. medium hardness, production shot). 
  • Blocks labelled "Blasted", "FreeDig", or "Backfill" will be assigned zeroed blast parameters. 

Tactical Scheduler Setup

Configuration Options

In Setup > Configuration Options, select 'Use Drills' to turn on Drill Scheduling. 

Extension Source

In Setup > Extension Source, select the Site Specific Extension that has been provided by Alastri. The extensions hold the logic for populating block-by-block drill quantities from user inputs. 

Misc Fields

In Setup > Misc Fields, create new Misc Fields to classify the blast blocks:

  • Surface Area
  • Presplit Perimeter
  • Blast Status
  • Hardness
  • Rig Type

Drilling Fields

In Setup > Drilling Fields, add reporting fields such as number of holes, length, volume, and so on. 

Drill Hole Types

In Setup > Drill Hole Types, add the hole types that will be encountered in the project. 

Map Fields

Map the reserves values into the new Misc Fields.

Refinements

In Setup > Refinements, parameter input tables are displayed for every hole type that is detected in the reserves. Enter the appropriate parameters for each hole type. 

...

Blast parameters and calculation methods may be configured in the Site Specific Extension. 

Drilling Dependencies

In Setup > Dependencies > Drilling, enter the dependencies to be used in each mine, pit, stage or bench. 

...

Info
*Blasting Delay can be made a variable in the Site Specific Extension if required.

Drill Types

In Setup > Drills, add the drill rig types to be used in scheduling.

  • Tick the availability types to be added as rows in the Calendar. 
  • Tick the hole types that can be drilled by each rig type. 

Incentives

In Setup > Incentives, add priority incentives to store the drilling sequence for each pit.

Constraints

In Setup > Constraints, add constraints to control blast stocks limits, drilling meters by pit or bench, and drill unit assignment by area. 

  • Constrain stocks blasted in the period with a Standard Constraint on drill volume. 
  • Constrain number of each drill type by pit or bench with an Agent Assignment Constraint.
  • Constrain drill quantities by pit or bench with a DrillSource Constraint.

Schedule Calendar

Drills

Enter the total number of drills and time usage by period. 

...

Info

Priority Incentives are defined in Setup > Incentives. The manual sequence is entered in Schedule > Animation > Priority Incentives. 

Constraints

Enter the values by period in each constraint. 

  • Constrain stocks blasted in the period with a Standard Constraint on drill volume. 
  • Constrain number of each drill type by pit or bench with an Agent Assignment Constraint.
  • Constrain drill quantities by pit or bench with a DrillSource Constraint.

Priority Sequencing

Go to the Animation tab and find the Priority Incentives panel in the top left corner. At the beginning of the schedule, edit the priority incentive for each pit and pre-assign the drill sequence for the entire pit. This way, whenever you assign a drill to this pit in Calendar > Constraints > Drill Assignments, it will pick up the sequence where the last drill left off. 

...