Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.


Info

This step is hidden if the scheduling mode is set to Truck Constrained in the Configuration Options.

When the user presses the button to run one period in the schedule, there are two passes happening behind the scenes.

  1. In the first instance, each Agent selects a mining sequence determined by the dependencies, incentives, and constraints. No destinations are assigned.
  2. In the second instance, an optimisation is run to determine the best destination for each ore parcel, using the Product Specifications as inputs.

The Product Specifications step allows the user to define the rules of the optimisation. Each rule becomes a new row in the Calendar; values for the rule are specified in Schedule > Calendar > Product Specifications.

Image Removed

Product Specifications in a sample iron ore project.

Cash Flows

Cash flows allow the user to specify an incremental reward or penalty for each (tonne / cube / ounce) of material sent to a destination. If two rules satisfy the same condition, then the cash flow is the sum of values in each rule.

Image Removed

Set the source, material, destination, and unit on which to apply the cash flow.

Cash Flows by Plant

This example allows the user to control the priority of the wet plant and dry plant, and prefer certain materials into each plant.

  • $30 reward per railed tonne from the dry plant.
  • $30 reward per railed tonne from the wet plant.
  • $10 reward per railed tonne of HG from the dry plant.
  • $10 reward per railed tonne of LG from the wet plant.

Image Removed

Cash flows on wet plant, dry plant, HG feed, LG feed.

...

Шаг Product Specifications (Спецификации на продукт) будет скрыт, если в шаге Configuration Options (Параметры конфигурации) режим планирования установлен на Constrain to Truck (Ограничения по самосвалам).

Когда пользователь нажимает кнопку для запуска одного периода в расписании, в программе происходят два прохода.

  1. В первую очередь, каждый агент выбирает последовательность добычи, определяемую зависимостями, предпочтениями и ограничениями. Без задания назначений.
  2. Во вторую очередь, запускается процесс оптимизации, чтобы определить самое подходящее назначение для каждого пакета руды, с использованием спецификаций на продукт в качестве вводных данных.

Шаг Product Specifications (Спецификации на продукт) дает пользователю возможность определить правила оптимизацииКаждое правило становится новой строкой в Календаре; значения для правила указаны в Schedule > Calendar > Product Specifications (Расписание Календарь > Спецификации на продукт).

Image Added

Шаг Product Specifications в примерном проекте разработки месторождения железной руды

Table of Contents

Финансовые потоки

Настройка финансовых потоков позволяет пользователю указать дополнительное вознаграждение или штраф за каждую единицу (тонну/куб/унцию) материала, отправляемого в пункт назначения. Если два правила удовлетворяют одно и то же условие, то финансовый поток будет представлять собой сумму значений в каждом правиле.


Image Added

Задайте источник, материал, назначение и единицу для применения финансового потока

Финансовые потоки по фабрикам

Эта опция дает пользователю возможность контролировать приоритет обогащению сухим и мокрым способом и отдавать предпочтение определенным материалам для каждой фабрики. См. пример ниже.

  • Вознаграждение в $30 за тонну, отгруженную с фабрики обогащения сухим способом.
  • Вознаграждение в $30 за тонну, отгруженную с фабрики обогащения мокрым способом.
  • Вознаграждение в $10 за тонну высокого сорта, отгруженную с фабрики обогащения сухим способом.
  • Вознаграждение в $10 за тонну низкого сорта, отгруженную с фабрики обогащения мокрым способом.

Image Added

Финансовые потоки по материалам, обогащеннным сухим и влажным способами, а также высокого и низкого сортов

Сумма этих значений показывает, что высокий сорт (HG) приносит 40 долларов с фабрики обогащения сухим способом и 30 долларов с фабрики обогащения моркым способом, тогда как низкий сорт (LG) приносит 30 долларов с фабрики обогащения сухим способом и 40 долларов с фабрики обогащения мокрым способом. Таким образом, оптимизатор предпочитает отправлять высокий сорт на фабрику обогащения сухим способом, но при необходимости может дополнить поставкой на фабрику обогащения мокрым способом.

Cash Flows by Material

This example prioritises feeding HG first, then MG, then LG, to maximise the returned metal content.

...

Cash flows for greedy metal recovery.

Cash Flow Values

Cash flow values are strictly relative. Setting all fields to '10' is the same as setting all fields to '10000'.

Users are encouraged to pick values that express the relative importance of each transaction. If high grade yields twice the revenue of low grade, give it twice the cash flow.

Cash Flows between Stockpiles

Movement between stockpiles incurs a default negative cash flow of (-1000) per bank cubic meter. This prevents the optimiser from going into circular rehandle loops.

...

Note

Be careful to only allow one-way passage of material between stockpiles. Do not incentivise the optimiser to engage in non-productive rehandle.

Grade Targets

Grade targets allow the user to specify a strict grade range, and place penalty multipliers on deviation from the target. Different destinations may have different grade targets. 

...

Grade targets on iron, alumina, and silica.

Grade Fields

Grade specifications can be set to reference any field in the database.

...

Info

To configure the dry/wet, rail/ship, lump/fine process stream options, see Setup > Processing Paths.

Insitu Fields

Use these fields on stockpiles and crushers when targeting a head grade.

ProcessStreams Fields

Use these fields to target product grades on stockpiles. Since the software does not know what crusher the stockpile will feed into, the user is required to specify the processing stream of the grade fields.

...

List of available Stockpile Grade Target fields for a sample Iron Ore project

Output Fields

Use these fields to target product grades through crushers. Since the software knows the process stream for each crusher, the 'Output' fields act as a wildcard to automatically select the corresponding grade fields.

...

Crusher Grade Target fields for a sample Iron Ore project

Grade Lower Limit

The final weighted average grade cannot be below this value.

...

Toggle upper and lower grade limits.

Grade Upper Limit

The final weighted average grade cannot be above this value.

  • Individual feed blocks can be higher than the maximum.
  • If multiple destinations are listed, individual destinations can be higher than the maximum.

Grade Target

The difference between the actual grade and the target grade is subject to a penalty multiplier specified by the user.

...

If Crusher A and Crusher B have different grade targets, then a single block will incur a different penalty depending on the destination. This penalty is summed with the Cash Flows to determine the reward or cost of blending materials into each destination.

Content Deviation Penalties

The value of the content deviation penalty should be considered relative to other grades, and relative to the Cash Flow values.

  • If the net grade penalty is greater than the crusher cash flow, then the crusher won't feed.
  • If the Fe grade penalty is greater than the Al grade penalty, then the optimiser may blow out Alumina to keep Iron on spec. This is because the penalty of dirtying Al is lower than the penalty of dirtying Fe.

Blend Target

Blend targets allow the user to specify a maximum or minimum ratio of some material into a crusher or stockpile.

...

Set the ratio limits, numerator field, denominator field, and destination.

Blend X up to 10%

This example targets a 10% LG blend into the crusher, but still feeds if there is no LG available.

...

Cash Flow incentive paired with a maximum Blend Target.

Recommended Usage

Take note of these behaviours when using blend ratios:

...