This page provides guidance on troubleshooting dependencies.
Table of Contents |
---|
Activity Sequences
Activities sequences set in the Activity Sequences step can be used to allow delays for other support activities.
...
Using the above setup:
24 hr delay is set between Drilling completion and Charging starting to allow for drill hole sampling.
96 hr delay is set between Drilling completion and Mining starting to allow for grade control blocking.
Showing Dependencies from the Animation tab, one can see that both Charging and Mining are waiting on their associated Activity Sequence delay.
...
Clicking on a block in the Animation tab, will automatically show Expand distance dependencies with pink arrows.
Showing Dependencies, one you can see that Mining of the bottom flitch is waiting on Mining for the adjacent solids.
...
Limits the number of benches that can be active in a given area.
...
Using the above setup, Mining has been restricted to a single bench but the Gantt has a digger scheduled to mine a second bench .Showing Dependencies, one (as shown below).
...
Selecting “Showing Dependencies” option from right click dropdown in the Animation tab, you can see that the lower bench is dependent on ALL solids on the bench above due to Max Active Benches.
...