Follow these steps to set up single destinations.
...
Setup > Settings
Tick Enable Dig Plans, and Enable Single Destinations
...
Setup > Settings > Enable Dig Plans & Single Destinations
...
2. Setup > Tables
Add Flitch and DigBlock level
...
Setup > Tables > include Flitch level and Dig level in reserves table.
3.
...
Setup > Destinations
Create the Destinations. These are the material types the dig blocks will be organised into.
Setup > Destinations > list material types for the grade control blockouts.
4.
...
Setup > Destination Cash Flow
Specify the ore revenue and dilution cost. These are the cash flows that calculate the most suitable dig block to assign a parcel to.
...
Setup > Destination Cash Flows > specify the ore revenue and dilution cost.
...
5. Setup > Phase Details
Assign Destination Cash Flow to each phase
...
Setup > Phase Details > assign cash flows to phases.
6. Designer Tab > Automated Dig Line Creation.
...