Adding Custom Dependency
Press the blue plus icon to add a New Dependency Set.
Rename the Dependency Set (i.e. Mining rules, Backfill rules, Land bridge rules).
Using the tree hierarchy on the top right, select the Successor record and double click on the Predecessor.
Select Predecessor and Successor Activities from the bottom right panel to apply custom dependencies to the specific activities.
Double click on the Predecessor record to confirm.
Set a Delay (in hours) to be kept between the specified activities, if applicable.
Activity | Description | Example |
---|---|---|
ProductionDrilling, ProductionCharging, ProductionBlasting | Normal scheduling activities. | Drilling on the 760 bench will happen after Blasting on the 770 bench. |
<PreBlastSolid>, <PreDigSolids>, <PostDigSolids>,<PostBlastSolids> | Meta activities, representing a state before or after, for example:
| All of the blasts on the 770 bench cannot start drilling until the blast 14 on the 720 bench is fully drilled, charged and blasted. These activities are mostly used to be able to know in the Schedule what state a block is in. |
Mining | For the Flitches and Dig levels, as well as for Dumps, only Mining activity is available as no other activities can be done prior. | See below the dynamic of the Schedule Dependencies based on Custom Activities input. |