When preparing reserves for further scheduling, we are interrogating created/imported phase solids against the block model to get data on tonnes, grades, metal content etc, but sometimes you may need to add extra properties to that.
The Phase Properties step provides option to create additional properties for each phase. This might be used to flag some phases for special treatment, such as backfill ramp solids vs. reserve solids.
...