The Dependencies setup tasks allow users to set different dependencies for a project. Dependencies control the logical order in which blocks are extracted from the pit and filled in the dump.
...
Step | Description |
---|---|
Phase adjacencies are used to ensure that a backfill dump does not encroach within the standoff distance of unmined blocks. | |
Set dependencies between blocks, and bench access, by ramp point or direction. | |
Allows user to plan multiple benches mining in a single phase. | |
Synchronize vertical offsets values between stages. | |
Specify dependencies between any two records, including upper level records. | |
Specify exclusion zones and blasting delays. This setup step only appears if in the Configuration Options step you ticked Use Dependencies option. |
...