Every project must have at least one crusher, which represents the commercial output of material from site.
...
To add crushers:
Go to Haul Infinity > Network tab:
Find or create a crusher called "Crushers/CR1".
Go to the Setup tab > Crushers step:
Press the green plus icon to add a crusher.
Rename the crusher to "CR1".
Select a processing stream from the dropdown, such as wet plant/dry plant.
In the Availability Types to Specify column toggle availability types to add to the calendar, such as "Planned/Unplanned Availability", "Use of Availability" and "Operating Efficiency".
Select a capacity field from the dropdown, such as "wetTonnes".
Info |
---|
Crushers must be represented by a node in Haul Infinity. The node name must follow the convention Crushers/myCrusherName. |
...
Adding Crushers
Crushers must be represented by a node in Haul Infinity.
...
In ATS, crushers can be added using plus icon in the toolbar, or imported directly from Haul Infinity.
Option | Description | Example | ||
---|---|---|---|---|
Adding Crushers manually | To add and remove crushers manually use the green plus and red minus buttons located in the top toolbar. The names in the Crusher Name column must follow this convention:
| |||
Adding Crushers from Haul Infinity | You can add all or missing crushers from Haul Infinity. For this, use the Add Missing Items button located in the top toolbar.
|
Processing Streams
Sometimes one real world crusher must be represented by multiple crushers in ATS, since each "Crusher" may only produce one product type.
In the Processing Stream column select one of the streams added in the Processing Path step.
...
Example
A mine has two crusher bin locations. Each crusher bin feeds both wet and dry plants. The site produces a Standard and a Special sale product.
...
Crushers:
CR1_wet_standard
CR1_dry_standard
CR1_wet_special
CR1_dry_special
CR2_wet_standard
CR2_dry_standard
CR2_wet_special
CR2_dry_special
Constraints:
CR1 crusher feed limit, across all CR1 streams
CR2 crusher feed limit, across all CR2 streams
Standard product tonnes limit, across all Standard streams
Special product tonnes limit, across all Special streams
Wet plant throughput tonnes limit, across all Wet streams
In the Schedule > Calendar, we leave each Crusher unrestricted in capacity, and control the feed to each bin via the Constraints.
Availability Types to Specify
In the Availability Types to Specify column toggle availability types to add and control in the Calendar, such as "Planned/Unplanned Availability", "Use of Availability" and "Operating Efficiency".
Types of availability include:
Planned Availability (PA),
Unplanned Availability (UPA),
Use of Availability (UA),
Operating Efficiency (OE) - Power/Engine On.
...
Capacity Field
The schedule calendar contains a capacity row for each stockpile. The capacity field is the unit of measurement of stockpile size, such as volume or tonnes.
...