Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

RU 🇷🇺

Table of Contents

Introduction

Keep these relationships in mind when making changes to the schedule logic and calendar values. 

Item

Description

Agent

Picks the blocks and executes schedule logic on them.

Dependencies

Only some blocks are available to mine at each moment.

Incentives

With the available blocks, prefer to mine some over others.

Destination Logic

With the selected block, find a destination.

Steps Logic

With the selected source and destination, 

  1. Optionally break the route into multiple legs (such as production and rehandle),

  2. Select a fleet for each leg.

Fleets

With each selected fleet, find a truck and loader combination with remaining hours.

Loader Types

With the selected loader, consume loader hours at the loader production rate.

Truck Types

With the selected truck, consume truck hours at the truck production rate.

Once the sum of movement between a source and destination hits a Constraint, then no more material may be moved between those points. 

...

Summary of issues that may be returned by the schedule logic:

Scheduling Mode

Issue Type

Cause

Solution

Optimise Products

Infeasible Solution

The optimiser could not find a destination for a material, either due to constraints or to product specifications.

Either reduce the ore mined or relax the capacities/constraints/grade limits that are constricting the movement

Invalid Cycle Time

Haul Infinity could not find a route.

Either there is no route in Haul Infinity, or the route contains steep segments/dynamic haulage

Overflow

The optimised destinations use more equipment hours than available.

Either reduce tonnage targets or reallocate equipment to shorter hauls

Constrain on Trucks

Constrained by Steps Logic

If a step rule uses multiple fleets, both fleets must have available hours.

Either reduce tonnage targets or reallocate equipment to shorter hauls

Stockpiles reclaim defaults to zero

Calendar > Stockpiles > Reclaim Target = 0

Manually set rehandle targets for each stockpile in each period