An Activity Sequences step can be used to set logical dependencies between activities, i.e., you can’t mine a blast until it has been drilled and blasted. These can be constrained to a particular record set, defined by the user.
...
Info |
---|
Subsets created in the Setup tab > Record Subsetsstep are available to be used here. |
Column | Description |
---|---|
Records | Select record subsets to apply the following dependency to |
Successor | The activity to follow the predecessor activity |
Predecessor | The activity to be completed before the successor activity |
Delay (h) | A delay, specified in hours, which will be applied to the successor activity once the predecessor activity has been completed |
To add an Activity Sequence:
...
Info |
---|
Activity Sequences can be added through scripts. These entries in the table will appear in bold blue and can’t be edited. |
...