With Spacial Conformetrics 2.0 and above, users can choose to Beginning and end schedule surfaces are required to determine conformance. These surfaces can come from external software or be generated directly through the Stage Plan steps in Alastri Spatial Conformetrics. One benefit of using Stage Plans is that you can account for actual mining direction in generated stage planswhen generating schedule surfaces. This means that , if a block is 50% scheduled and 50% mined, then it can achieve 100% conformance regardless of the original originally scheduled mining direction.

Stage Plans Setup Task consists of three steps:

Child pages (Children Display)
Info

Stage Plans steps are only visible if Generate Stage Plans option is flagged in the Settings step.

Stage Plans Setup Task, consists of three steps: