An activity sequence can be used to set logical dependencies between activities, i.e., you can’t mine a blast until it has been drilled and blasted. These can be constrained to a particular record set, defined by the user.
...
Setup > Activity Sequences.
Info |
---|
Subsets created in Setup > Record Subsets are available to be used here. |
...
Column
...
Description
...
Records
...
Select record subsets to apply the following dependency to.
...
Successor
...
The activity to follow the predecessor activity.
...
Predecessor
...
The activity to be completed before the successor activity.
...
Delay (h)
...
A delay, specified in hours, which will be applied to the successor activity once the predecessor activity has been completed.
To add an Activity Sequence:
Press the blue plus button.
Configure the sequence as per table above.
...
Шаг Activity Sequences (Последовательности операций) можно использовать для установки логических зависимостей между операциями, например, что нельзя разрабатывать взрывной блок, пока он не будет пробурен и взорван. Эти зависимости можно ограничить определенным набором записей, заданным пользователем.
...
Info |
---|
Здесь можно использовать подмножества, созданные в шаге Record Subsets (Подмножества записей) вкладки Setup. |
Столбец | Описание |
---|---|
Records (Записи) | Выбор подмножества записи, к которому будет применена зависимость |
Successor (Последующая) | Операция, следующая за предшествующей |
Predecessor (Предшествующая) | Операция, которая должна быть завершена до начала последующей |
Delay (h) (Задержка (ч)) | Задержка в часах, которая будет применена к последующей операции после завершения предшествующей |
Для добавления последовательности операций:
Нажмите синюю иконку со знаком плюса.
Настройте последовательность в соответствии с таблицей выше.
Info |
---|
Последовательность операций можно добавить через сценарии. Такие записи будут отображены жирным синим и не могут быть отредактированы. |