Bench Offsets may be used to force a delay and minimum or maximum vertical lag between phases. 

...

Setup > Bench Offsets

To add a Bench Offset:

...

  • Press the blue plus icon to add a new rule group.

  • Rename the rule group (i.e. mining rules, backfill rules, land-bridge rules).

  • Using the tree hierarchy on the right, select the successor record and double click on the predecessor.

  • Set the delay in hours.

  • Set the Vertical Offset in metres:

    • Negative to keep the successor elevated over the predecessor

    • Positive to keep the predecessor elevated over the successor

  • Verify the dependencies in the Preview panel.

...

Настройки, приводимые в шаге Bench Offsets (Смещения уступа) могут использоваться для установки задержек и обеспечения минимального и максимального вертикального смещения между фазами.

...

Для добавления зависимости смещения уступов:

  1. Нажмите синюю иконку со знаком плюса для добавления нового набора зависимостей.

  2. Переименуйте этот набор (например, правила разработки, правила обратной засыпки, правила штабелирования).

  3. Из иерархии древовидной структуры справа выберите последующую запись (Successor) и дважды щелкните по соответствующей предыдущей записи (Predecessor).

  4. Задайте задержку в часах.

  5. В столбце Vertical Offset установите вертикальное смещение в метрах:

    1. отрицательное — чтобы последующая запись была выше предшествующей,

    2. положительное — чтобы предшествующая запись была выше последующей.

  6. Проверьте зависимости на панели предварительного просмотра Preview.

Info

Каждый уступ на высотной отметке «Е» на этапе Successor (Последующий) становится зависимым от уступа на отметке «Е + смещение» на этапе Predecessor (Предшествующий). Смещения могут быть положительными или отрицательными.