Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

Follow these steps when the crusher is feeding, but for some reason the grades out of acceptable limits.

If the schedule has these issues, resolve them first:

Check Если подача в дробилку установлена, но содержания по каким-либо причинам выходят за допустимые пределы, выполните приведенные ниже действия.

Сначала решите приведенные ниже ошибки, при наличии:

Шаг 1: Setup > Map Fields > Parcel

...

  • Make sure that tonnes and grades are mapped in all Mining and Processing fields. Missing mappings are evaluated as zeroes, which may affect the optimisation.

Image Removed

Check for missing mappings in product tonnes and grades.

Check 2: Reserves tab > Data panel.

  • Do a quick sanity check in the Reserves tab on the schedule inventory. Sometimes the block model has errors, or their may be incorrect call factors in Setup > Refinements.

Image Removed

Check for rubbish values in the Reserves tab.

...

Mapping (Сопоставление полезных компонентов)

  • Убедитесь в правильности сопоставления тонн и содержаний в полях Mining и Processing. Не сопоставленные поля оцениваются как нулевые, что может повлиять на процесс оптимизации.

...

Шаг 2: Вкладка Reserves > панель Data

  • Выполните быструю проверку правильности запасов в календарном плане во вкладке Reserves. Вы можете обнаружить ошибки в блочной модели или неправильные факторы сходимости, установленные в Setup > Refinements.

...

Шаг 3: Setup > Opening Inventories

  • Make sure that tonnes and grades are populated in all Mining and Processing fields. Missing entries are evaluated as zeroes, which may affect the optimisation.

Image Removed

Check for missing grades and tonnes in Opening Inventories.

...

  • Убедитесь в правильности сопоставления тонн и содержаний в полях Mining и Processing. Не сопоставленные поля оцениваются как нулевые, что может повлиять на процесс оптимизации.

...

Шаг 4: Schedule > Calendar > Stockpiles

  • Stockpiles may be forced to reclaim material if the closing capacity is less than the opening inventory. This can cause otherwise rubbish material to be forced into the feed, and contaminate the grades.

Image Removed

Check for forced reclaim due to closing capacity limits.

...

  • Если значения для запасов на конец периода ниже, чем на начало, может произойти принудительная отгрузка материала из рудного склада. Это может привести к нежелательному попаданию в подачу дробилки лишних материалов и последующему загрязнению сорта.

...

Шаг 5: Schedule > Calendar > Constraints

  • Good material may be blocked from the crusher if there are constraints on feed. This can cause otherwise rubbish material to make up the difference.

Image Removed

Check for constraints blocking specific stockpiles or materials from feeding.

Info

Always check the constraint configurations in Setup > Constraints > Configuration. It is extremely common to see mistakes in the setup have domino effects in the schedule.

...

  • При наличии ограничений на подачу может произойти блокировка «хорошего» материала и попадание «плохого» для восполнения разницы.

...

Info

Не забывайте проверять конфигурацию ограничений в столбце Configuration на шаге настройки Constraints. Ошибки настройки провоцируют цепь ошибок в процессе планирования, как «эффект домино».

Шаг 6: Schedule > Calendar > Product Specifications

  • Check for unachievable or conflicting product specifications.

...

  • Проверьте на наличие недостижимых или противоречивых показателей.

Рекомендации по правильной настройке этого шага см. в разделе TS. Спецификации на продукт for tips on correct setup.

Image Removed

Example: crusher cannot simultaneously feed 80% LG and maintain 60% Fe.

...

Шаг 7: Schedule > Reporting >

...

  • Check mined grades and closing stockpile inventories.

If the available tonnes do not meet product specifications, then either change the mining locations or relax the product limits to allow feed.

...

разработанные содержания и запасы

  • Проверьте разработанные содержания и запасы на складе на конец периода.

При несоответствии доступных тонн спецификациям на продукт, либо измените места разработки, либо ослабьте ограничения для продукта, чтобы разрешить подачу.

Шаг 8: Schedule > Calendar >

...

  • Go to Setup > Constraints and constrain all movements except for the expected movement.
  • Go to Calendar > Constraints and zero the constraints to force material into the expected path.
  • Run the schedule.
  • Read the failure message.

Image Removed

...

принудительный отказ оптимизации

Создайте принудительный отказ оптимизации и прочитайте сообщение об ошибке.

  • Перейдите Setup > Constraints и ограничьте все перемещения, кроме ожидаемого.

  • Перейдите Calendar > Constraints и обнулите ограничения, чтобы заставить материал пойти по ожидаемому пути.

  • Запустите планирование.

  • Прочитайте сообщение об ошибке.

...