Follow these steps to set up single destinations.

...

  1. Setup > Settings

Tick Enable Dig Plans, and Enable Single Destinations

...

Setup > Settings > Enable Dig Plans & Single Destinations

...

2. Setup > Tables

Add Flitch and DigBlock level

...

Setup > Tables > include Flitch level and Dig level in reserves table.

3.

...

Setup > Destinations

Create the Destinations. These are the material types the dig blocks will be organised into.

Image Added

Setup > Destinations > list material types for the grade control blockouts.

4.

...

Setup > Destination Cash Flow

Specify the ore revenue and dilution cost. These are the cash flows that calculate the most suitable dig block to assign a parcel to.

...

Setup > Destination Cash Flows > specify the ore revenue and dilution cost.

...

5. Setup > Phase Details

Assign Destination Cash Flow to each phase

...

Setup > Phase Details > assign cash flows to phases.

6. Designer Tab > Automated Dig Line Creation.

...

Designer > top button ribbon > Automated Dig Line Creation.

...