Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

With a new Gantt report option, end users can create fully customisable Gantt reports.

...

General Settings

Main setting of Gantt report in the Result tab

Gantt Bar Method

Select from the dropdown preferred Gantt Bar Method “Scheduled” or “FullPeriod”.

  • Scheduled will use the date/times as they are actually scheduled in the software.

  • FullPeriod will assume actions are taken over the duration of the period rather than at the instant they are actually done.

Info

Depending on the model setup, FullPeriod may give a better representation of the scheduler’s intent in ATS, but for better visualization of results in APS, “Scheduled” method is recommended.

Result Panel Column Section Max Width

Specify the desired maximum width of the section with columns in the Result tab.

Page Row Height

Specify the desired height of rows in the Page list.

Info

To display Page list, select “Page” as location in the Groupings tab.

Gantt Row Height

Specify the desired height of rows in the Gantt.

Compress Blanks

If selected, when a value does not apply to a grouping at a level, a blank will be used instead.

This can lead to a chain of nodes which just say “blank” before you get to the userful node at the end of the chain. If compress blanks is enabled, this will remove the intermediate blank nodes for a cleaner look.

Example, if you’re looking at Stockpiles and Reserves:

  • Reserves/Mine1/Pit1/Stage1/450/hg (either way)

  • Stockpiles/SP1/blank/blank/blank/hg (Compress Blanks Off)

  • Stockpiles/SP1/hg (Compress Blanks On)

Split Noncontiguous Chronologically Sorted Leaf Tasks

This option will split and duplicate leaf tasks (tasks with no child tasks) if all of the following are true:

  • The option is enabled.

  • The task is done at multiple different times, and other tasks occur between the start and end of the task.

  • The level is chronologically sorted.

This option generally only makes sense if the leaf tasks are dig or blast blocks being operated on by a single Agent. If this option is enabled and an agent finishes half block A, then does block B, and then returns to finish block A, there will be two rows for task A, rather than just one.

Show Horizontal Lines

Flag this box to display or hide horizontal lines between rows in Gantt.

Horizontal Line Color

Optionaly, specify a color and opacity of a horizontal line.

Show Multi-Shading Badge

Flag this box to display or hide multi-shading badge.

Multi-Shading Badge Color

Optionaly, specify a color and opacity of a multi-shading badge.

Rostered Delays Settings

Settings of Delays display in the Results tab

Shading

Group Header

Select “(none)” of or “<Default Delays>” shading.

  • <Default Delays> reflects delays colors set in the Delays setup step.

Image Removed

Hatch Pattern

Optionaly, select a different hatch pattern for the delays shading.

Opacity

Optionaly, specify a different hatch pattern for the delays shading.

  • You can also add custom Delay Shading in the Shadings tab, and select it from the Shading dropdown.

Image Added
Info

Note that in order to see Rostered delays in the Gantt report, the Agent must be added as Group Option in the Grouping tab, otherwise no delays will be displayed for Activity/Source/Destination group options.

Hatch Pattern

Optionaly, select a different hatch pattern for the delays shading.

Opacity

Optionaly, specify a different hatch pattern for the delays shading.

Group Header

Settings of Groups display in the Results tab

Text Color

Optionally, specify a color of text for “Groups” header in the Result tab.

Back Color

Optionally, specify a background color for “Groups” header in the Result tab.

Text

Optionally, change “Groups” header text in the Result tab.

Width

Optionally, specify a width of the Groups column in the Result tab.

Font

Family

Optionally, specify font, size and style of the “Groups” header text.

Size

Style

Periods

Periods display settings in the Result tab

Period Set

Select which period set will be used in Gantt report. This will determine the periods shown in the timeline at the top.

Available Period sets are configured in the Periods setup step.

Start Period

Select a period to start your custom Gantt report.

End Period

Select a period to finish your custom Gantt report.

Left Timeline Buffers (Pixels)

The blank space on the left of the timeline to leave room for labels.

Right Timeline Buffers (Pixels)

The blank space on the right of the timeline to leave room for labels.

Schedule Start Guide

Setting of the red dashed line at the start of the schedule

Enabled

Leave flagged (default), if you want the red dashed line to be shown at the start of the schedule, otherwise unflag this option.

Color

Optionally, specify a color of the schedule start guide line.

Line Style

Optionally, specify a style of the schedule start guide line.

Line Width

Optionally, specify a width of the schedule start guide line.

Dash Multiplier

Optionally, specify a dash multiplier of the schedule start guide line.

Schedule End Guide

Setting of the red dashed line at the end of the schedule

Enabled

Leave flagged (default), if you want the red dashed line to be shown at the start of the schedule, otherwise unflag this option.

Color

Optionally, specify a color of the schedule end guide line.

Line Style

Optionally, specify a style of the schedule end guide line.

Line Width

Optionally, specify a width of the schedule end guide line.

Dash Multiplier

Optionally, specify a dash multiplier of the schedule end guide line.

Axis Display

Major

Settings of the first row in the timeline.

Enabled

Leave flagged (default), if you want the first line (with Year and Month) to be shown at the very top of the schedule, otherwise unflag this option.

Text Color

Optionally, specify a color of the Major Axis Header text in the Result tab.

Back Color

Optionally, specify a background color of Major Axis Header text in the Result tab.

Header Font

Optionally, specify font, size and style of the Major Axis Header text.

Guide Line

Settings of the Guide Line between Major periods (only visible if Major Axis display is enabled).

Optionally, specify font, color, style, width and dash multiplier of the Major Axis Guide Line.

Minor

Settings of the second row in the timeline.

Enabled

Leave flagged (default), if you want the second line (with Dates) to be shown at the top (middle row) of the schedule, otherwise unflag this option.

Text Color

Optionally, specify a color of the Minor Axis Header text in the Result tab.

Back Color

Optionally, specify a background color of Minor Axis Header text in the Result tab.

Header Font

Optionally, specify font, size and style of the Minor Axis Header text.

Guide Line

Settings of the Guide Line between Minor periods (only visible if Minor Axis display is enabled).

Optionally, specify font, color, style, width and dash multiplier of the Minor Axis Guide Line.

Period

Settings of the third row in the timeline.

Enabled

Leave flagged (default), if you want the third line to be shown at the top (bottom row) of the schedule, otherwise unflag this option.

Text Color

Optionally, specify a color of the Periods Axis Header text in the Result tab.

Back Color

Optionally, specify a background color of Periods Axis Header text in the Result tab.

Header Font

Optionally, specify font, size and style of the Periods Axis Header text.

Guide Line

Settings of the Guide Line between Periods (only visible if Periods Axis display is enabled).

Optionally, specify font, color, style, width and dash multiplier of the Periods Axis Guide Line.

Even Back Color

Allows you to alternate background colors of the Gantt each period. This may be useful for night/day shift.

Odd Back Color

Color Badges

Leave flagged (default), if you want colored periods badges to be shown at the top (bottom part) of the schedule, otherwise unflag this option.

...

Info

A multi-Activity label can be only be used next to a Gantt bar - it cannot be used in a column.

Shadings tab

Info

Note that in order to display Multi-Activity labels, in the Groupings tab the first Group Set must be “Activity”.

Shadings tab

In the Shadings tab, you can add shading options to your Gantt. There are different types of shadings: DataSource, Source, Destination, Agent, Parcel, Activity and Delay.

...

In the bottom part of the Groupings tabc tab, configure how Group sets will appear in the resulting Gantt report.

Field

Description

Group Set #

Group set number as per level number, specified in the Group column above. If several records are added to the same level, they will be displayed as Item #1, Item #2, Item #3, etc.

Use the blue arrows to move Group Sets to the right/left.

Image Removed

Image Added

  • Note that in order to display Multi-Activity labels, the first Group Set must be “Activity”.

Location

You can choose for the first grouping to be allocated to a Page instead of the Gantt. This will create a panel on the left of the Gantt, and you can switch between the items there.

Info

Note, that only the first Group Set’s location can be set to Page.

Collapsed

Determines whether this node in the tree is expanded or not.

Name Separator

Specify a symbol for name separator to be used between name levels.

Tree

Colors and Fonts settings for the Tree items in the Result tab.

Text/Background Color

Optionally, specify text and background colors to be applied to the tree records.

Font

Optionally, specify font, size and style of the tree records.

Bars

Shadings and Labels settings for Gantt bars in the Result tab.

Shading

You can choose from one of the Shadings options (created in the Shadings tab). Alternatively you can choose <Continuous/Discrete Solid> and then choose a color for the bar. You can also choose “(none)”, in which case no bar will appear on the row.

There are certain types of shadings that can only be shown if at the level the shading is applied has been filtered down to a single activity either through the selections at a level above or through the Filters tab.

  • Note that the final Group Set must have a shading other than “(None)”, otherwise you’ll get an error message

Left/Right Labels

Choose a label that will appear on the left and/or right of the Gantt bar. This can be a multi-label or a single label.

...

Two functions are available in the Gantt report Result tab:

Export to PDF

...

  1. Press Export to PDF button and select one of the printing templates preconfigured in the Setup > Printing tab (see the description in the section “Printing tab” above

...

  1. ).

  2. Specify a saving path and review the exported Gantt report.

...

Note that depending on your machine display settings, in the generated PDF file you may see grey sections covering some parts of the data. If it causes any inconveniences and data loss, change your display custom scaling to 100 % (in System > Display > Scale > Custom scaling).

...

Row Order

In the Result tab, click the Reorder Rows button to show Row Ordered dialog shown below.

...