20.4.452 - Early Access Release

Alastri is pleased to announce the release of its latest versions of software.

Alastri Production Scheduler 20.4.

...

452

Major Improvements

...

Part of schedule requiring rerun will show as orange

  • Blasting Improvements

    • Users can now manually schedule blasts in a blast window, even if they are not yet available for blasting.

    • The Blasts row will always display the blasts which are scheduled. After running a schedule the icon on the left will update, indicating if the requested blast was actually completed.

    • Blast windows can be moved and updated without needing to re-run the schedule. Production Scheduler will attempt to display the blasts that are predicted to be available at the current blast window.

...

Users can add blasts manually to a blast window.

...

Blast windows will always display the scheduled blasts. After running the schedule, an icon indicates if the blast was actually completed.

...

Auto-blast windows update when moved, always displaying currently available blasts.

  • New Default Gantt Display label options

    • There are two new default options to choose from when configuring the Gantt display, “<FullNameDefault>” and “<ParcelDefault>”.

...

...

Max Agent Rate is now available per sequence in the Gantt

  • Truck Assignments

    • A new setup task “Truck Assignments” has been added.

...

...

...

Set Single Destinations per parcel

...

  • Filter Chrono reports by Blast/Dig Solid text fields https://alastri.atlassian.net/browse/PS-1333

    • Users now have the ability to filter Chrono reports by Blast/Dig Solid text fields that they have created on the “Fields” setup task.

...

  • 'Lock or Freeze' Surfaces in Sequence Painter https://alastri.atlassian.net/browse/PS-1424

    • Users now have the ability to 'Lock or Freeze' Surfaces in Sequence Painter to allow users to choose blocks under a visible surface.

...

New Reporting items

...

Rapid Reserver 20.4.

...

452

Improvements

...

Grade Control setup is now all in one dialog.

...

Strip Renamer tool is now available in the Designer.

...

  • Phase Details

    • Depletion surface is no longer assigned in Phase Details.

    • Use ‘Show Depleted Solids’ checkbox to toggle display of original and depleted phase solids in the viewport.

  • Bench Preconditioning

    • New viewport toolbar option to trace over existing lines to create a polygon has been added

    • New option to 'remove' material added to the existing 'send up/down' actions.

    • Users can customise the colours displayed in the Bench Preconditioning viewport.

...

Users can now exclude material at the bench level in Bench Preconditioning

...

Alastri Tactical Scheduler 20.4.x

Spatial Conformetrics 20.4.

...

452

Improvements

Haul Infinity 20.4.452

No changes for this release

Alastri Tactical Scheduler 20.4.452

  • It is now possible to select multiple phases and paste mappings into them in the Map Fields step.

  • It is now possible to create scripted custom dependencies.

  • It is now possible to specify phase adjacencies through a script.

  • Scheduling time and memory consumption is decreased on most projects, with projects using loader agents seeing the largest benefit.