Adding Guidance Sets

Guidance sets can be created in one of two ways:

New Guidance Set

Import from Micromine Beyond

Create a new, empty Guidance Set

  • To be filled with EOP surfaces from either Layers or from imported non-solid surfaces.

  • Import directly from a Micromine Beyond “.tridb” file

    • Automatically generates EOP surfaces and assigns periods to these surfaces.

Errors

Make sure your Guidance Sets names are not duplicated neither empty, otherwise you’ll get an error message preventing you from proceeding through the setup:

“Some guidance sets contain duplicate names, including
Tip

This feature allows users to provide a strategic guidance to the scheduling sequence.

By providing a set of end-of-period surfaces and target periods for these surfaces, the user can define which blocks should have priority for scheduling consideration.

Table of Contents
Image Removed

Overview

  • Allows users to specify which blocks should be mined by which period.

  • Maps end-of-period surfaces against blocks, assigning periods to blocks that are above an end-of-period surface.

  • Configure how strongly the schedule should adhere to these in the Schedule > Calendar tab > Guidance rows.

Enabling Guidance

This feature is optional and must be enabled or disabled by the flag in the Configuration options setup step.

When enabled, new setup step Guidance will appear in the Setup task list.

Note that this option is disabled by default.

Image Removed

Configuring Guidance Sets

Tip

Guidance Sets are collections of EOP surfaces. These are largely for organisational purposes only - all EOP surfaces are combined into a single collection when target periods are being assigned to blocks.

Эта функция позволяет обеспечить стратегическое направление последовательности планирования.

Предоставив набор поверхностей на конец периода и целевые периоды для этих поверхностей, пользователь может определить, какие блоки должны иметь приоритет при составлении плана.


Table of Contents
Image Added

Общее представление

  • Позволяет указывать, какие блоки должны быть отработаны в какой период.

  • Сопоставляет поверхности конца периода с блоками, назначая периоды блокам, которые находятся над поверхностью конца периода.

  • Позволяет настроить, насколько строго план должен придерживаться этих ориентиров, в План > вкладка Календарь > строки Guidance (Ориентир).


Активация использования стратегического ориентира

Эта функция является необязательной и включается или отключается с помощью флага на шаге настройки Параметры.

Если эта функция включена, в списке задач настройки появится новый шаг настройки - Ориентир.

Обратите внимание, что по умолчанию эта опция отключена.

Image Added

Настройка наборов поверхностей

Tip

Наборы ориентиров - это группы поверхностей на конец периода. В основном, они используются в организационных целях - все поверхности по концам периодов объединяются в одну сборку после назначения целевых периодов блокам.

Добавление наборов ориентиров

Наборы ориентиров могут быть созданы двумя способами:

Новый набор ориентиров

Импорт из Micromine Beyond

Создайте новый пустой набор ориенторов

  • для заполнения поверхностями на конец периода из панели Слои, либо импортированными поверхностями (не солидами).

Импортируйте напрямую из файла Micromine Beyond в формате".tridb".

  • автоматически генерирует поверхности на конец периода и назначает периоды для этих поверхностей.


Возможные ошибки

Убедитесь, что имена ваших наборов ориентиров не дублируются и не пусты, иначе вы получите сообщение об ошибке, препятствующее продолжению настройки:

“"Следующие наборы ориентиров имеют повторяющиеся имена: <(New Guidance Set 1)>”.

“Some guidance sets contain empty names”.

Image Removed

EOP Surfaces

Tip

EOP (End of Period) surfaces are surfaces which represent the expected or planned state of the pit by the end of a certain date.

Each EOP surface can have a Period assigned to them, which indicates that all blocks above this surface must be mined by the end of the assigned period.

Note

When multiple guidance sets are present, these are all condensed into a single large set for the purposes of calculation. Each block is assigned the earliest period from all guidance sets present.

Period Selection

Left-click on the row in the Period column. A drop-down list of period selections will open. Scroll up to select a period Before Plan, or down to select a period that is not part of the planning horizon considered in the model.

Multi selection

To assign one period to several surfaces, select them from the list using <CTRL> and <SHIFT> keys and select a period for the whole group in the lower panel. When assigning a single period to a selected group, the upper field will show “(multiple values)”.

Image Removed

Records panel and Viewport

In the Records panel, select the levels/records or Record Subsets you want to display in the Viewport.

Navigating through the viewport and the tree structure of the records is the same as in other steps. For more information, see UI. Tree Structure and Viewport.

Layers panel

The Layers panel is used to import and display any relevant surfaces and solids. For more information, see in the section UI. Layers/Overlays panel.

Data panel

Data panel is used to review mining properties of the selected records. For more information, see in the section UI. Data panel.

(lightbulb) To hide any one or several of these panels, use the pin icon provided in the upper right corner of each panel.

Image Removed

Note that you don’t see any updated guidance-based data in this setup step. The software calculates what period each reserve block should be mined by only when moving to the next setup item.

Calendar Inputs

Tip

Calendar inputs allow users to control how much influence end of period surfaces have on the schedule.

Guidance

To configure and review guidance impact on the schedule outcome, navigate to the Schedule > Calendar tab > Guidance rows. See the explanation below.

Period Matching Incentive

Schedule will focus on matching each individual period. Higher values will mean that blocks assigned a period to be mined will be given a higher priority, provided that the targeted period has not already been reached.

Period Match Lookahead

How many future periods impact the schedule. Blocks with assigned periods later than this many periods relative to the current period will be ignored. The closer the current period is to the block’s targeted period, the higher the incentive applied against the block.

Delayed Block Incentive

Schedule will increase the incentive on blocks that are behind plan. The more periods have passed between the block’s target period and the current period, the stronger the incentive.

Image Removed

Agents

Navigate to the Agents section to set the Strategic Guidance Weight for each Agent.

Strategic Guidance Weight

How strongly each agent will follow the guidance.

Image Removed

Scenarios

To compare different inputs outcomes in the same project, you can create several Scenarios, for example, with different incentives and weights. For more information, see the section TS. Schedule tab > Scenarios panel.

Image Removed

Animation

In the Animation tab, review how the scheduled mining is following the strategic guidances.

Reserves Shading

Default <Strategic Guidance> shading allows users to see what period is assigned as the target period of each block

"Некоторые наборы ориентиров имеют пустые имена."

Image Added


Поверхности на конец периода

Tip

Поверхности на конец периода (EOP) - это поверхности, которые представляют собой ожидаемое или запланированное состояние карьера к концу определенной даты.


Каждой поверхности может быть присвоен Период, который указывает, что все блоки над этой поверхностью должны быть отработаны к концу назначенного периода.


Note

При наличии нескольких наборов ориентиров, для целей расчета все они объединяются в один большой набор. Каждому блоку присваивается самый ранний период из всех имеющихся наборов ориентиров.


Выбор периода

Щелкните левой кнопкой мыши по строке в столбце Период. Откроется список выбора периода. Прокрутите список вверх, чтобы выбрать период "До начала плана", или вниз, чтобы выбрать период, который не входит в горизонт планирования, рассматриваемый в модели.

Мультивыбор

Чтобы назначить один период нескольким поверхностям, выделите их в списке с помощью клавиш <CTRL> и <SHIFT> и выберите период для всей группы в панели снизу. При назначении одного периода для выбранной группы в верхнем поле будет показано "(multiple values)" (несколько значений).

Image Added

Панель уровни и область просмотра

В панели Уровни выберите

На панели "Записи" выберите уровни/записи или группы уровней, которые вы хотите отобразить в области просмотра.

Навигация по области просмотра и древовидной структуре уровней такая же, как и в других шагах. Для получения дополнительной информации см. раздел UI. Древовидная структура уровней и область просмотра.

Панель Слои

Панель Слои используется для импорта и отображения применимых поверхнойтсей и солидов. Для получения дополнительной информации см. раздел UI. Панель Слои.

Панель Данные

Панель Данные используется для отображения информации по выбранным уровням/блокам. Для получения дополнительной информации см. раздел UI. Панель данных Data.


(lightbulb) Чтобы скрыть любую из этих панелей или несколько из них, используйте значок булавки, расположенный в правом верхнем углу каждой панели.

Image Added

Обратите внимание, что на этом шаге настройки вы не увидите обновленных данных, полученных на основе применения ориентиров. Программа рассчитывает, к какому периоду должен быть отработан каждый блок запасов, только при переходе к следующему этапу настройки.


Календарь

Tip

Вводные данные в Календаре позволяют пользователям контролировать, насколько сильно поверхности на конец периода влияют на план.

Guidance (Ориентир)

Чтобы настроить и просмотреть влияние ориентира на результат выполнения плана, перейдите во вкладку План > Календарь >строки Guidance. Их объяснение см. ниже.

Period Matching Incentive (Стимул соответствия периоду)

План будет фокусироваться на соответствии каждому отдельному периоду. Более высокие значения означают, что блоки, назначенные на определенный период, будут иметь более высокий приоритет, при условии, что целевой период еще не достигнут.

Period Match Lookahead (Соответствие последующим периодам)

Сколько будущих периодов влияет на план. Блоки с периодами назначенными позже, чем это количество периодов относительно текущего периода, будут игнорироваться. Чем ближе текущий период к целевому периоду блока, тем выше стимул, применяемый к блоку.

Обратите внимание, что значение по умолчанию "1" означает, что поиск будет соответствовать текущему периоду, без рассмотрения последующих. Ввод "2" означает, что механизм оптимизатор будет смотреть вперед на один месяц и т.д. Вы не можете ввести "0".

Delayed Block Incentive (Стимул для отложенных блоков)

План усиливает стимул для блоков, которые отстают от плана. Чем больше периодов прошло между целевым периодом блока и текущим периодом, тем сильнее стимул.

Image Added

Agents (Агенты)

Перейдите в раздел Агенты, чтобы установить значение весомости стратегического ориентира для каждого агента.

Strategic Guidance Weight (Вес стратегического ориентира)

Насколько строго каждый агент будет следовать данному ориентиру.

Image Added


Сценарии

Чтобы сравнить результаты разных вводных данных в одном и том же проекте, можно создать несколько сценариев, например, с разными стимулами и весами. Для получения дополнительной информации см. раздел TS. Вкладка Schedule > панель Сценарии.

Image Added

Анимация

Во вкладке Анимация просмотрите, как план отработки выполняется в соответствии с стратегическим направлением.

Цветовая заливка запасов

Новая стандартная цветовая заливка <Strategic Guidance> позволяет увидеть, какой период назначен в качестве целевого периода каждого блока.