Optimisation rules set in the Flow Optimisation step tell the software user’s display preferences (grades, blends, tonnes) when calculating destinations and product handling.

...

More details and examples of CashFlows see here.

Max Rate

Max Rate limits the optimiser to a specific rate for an instant in time.

...

Note

Be careful which the PlantAgent optimisation in the Calendar since it can create bottlenecks if the PlantAgent rate is lower than Crusher downstream.

In the example below, when reducing the PlantAgent’s max rate to 1000wt/h vs 5000wt/h Crusher’s rate, it creates bottleneck at the Crusher downstream since the Stockpile is getting filled faster than can be reclaimed to feed the Crusher:

It causes reduction of the material being fed to the Crusher upstream to allow for the Stockpile reclaiming at the reduced rate:

Image RemovedImage Added

In the Destinations tab it is also visible that the stockpile is being built faster than could be reclaimed:

...