Since the PlantAgent is not involved in any Expit movement, it won't consume any haulage units' hours, and doesn’t require being assigned in the Trucks Assignment step.

...

Flow Chart

Tip

The Plant Agent controls Post Crusher movements, that are not covered by Destination rules, but drawn manually in the Flow Chart step.

...

Transactions performed by the PlantAgent are controlled by the optimization rules in the Calendar.

...

This sort of control is optional. If not controlled in the Calendar, it will default to the upstream or downstream site items rates.

...

Note

Note

Be careful which the PlantAgent optimisation in the Calendar since it can create bottlenecks if the PlantAgent rate is lower than Crusher downstream.

In the example below, when reducing the PlantAgent’s max rate to 1000wt/h vs 5000wt/h Crusher’s rate, it creates bottleneck at the Crusher downstream since the Stockpile is getting filled faster than can be reclaimed to feed the Crusher:

Image Added

It causes reduction of the material being fed to the Crusher upstream to allow for the Stockpile reclaiming at the reduced rate:

Image Added

In the Destinations tab it is also visible that the stockpile is being built faster than could be reclaimed:

Image Added

Reporting

Filter by the “PlantAgent” Agent in the Pivot report to see all material movements it controls:

...

Steady States

Plant Agent is not involved in expit movements. To check the transactions that it performs at a particular point in time, go to the Steady States tab.

...