Table of Contents |
---|
...
Verify the dependencies in the Preview panel.
See the table below for a description of the main items, as well as the principles of working with this type of dependency.
Activity | ViewExample | Description |
---|---|---|
Adding New Dependency Set |
| |
Selecting dependent levels |
| |
Viewing a rule | The levels selected on the right will be displayed in the Rules panel in the middle. Use the Preview panel at the bottom to view verify all the levels included in the selected rule.
| |
Setting Vertical Offset |
See the Illustration below. | |
Setting Time Delay | Specify the necessary time delay (in days) that should be kept after the selected level is mined (if necessary). For example, wait 30 days after completing Stage 1 before starting mining on Stage 2. | |
Exporting and importing Dependency Rules | Created dependencies can be exported from one project and imported into another. To do this, use the export and import icons in the top right corner. Dependency rules are transferred in the ".depxmldepoffxml" format. |
Anchor | ||||
---|---|---|---|---|
|
...