As outlined in Domain Mappings, Spatial Conformetrics looks at the intersection of a production solid and a schedule solid generated from a set of start and end surfaces. Creating the production and schedule solids is completed in the "Surface Sets" step.

Creating a Surface Set

  1. Press the blue plus button located in the toolbar of the Polygons panel

  2. Give the surface set a meaningful name, i.e., "Pit1/Stage1".

  3. Provide the relevant surfaces, which are outlined below.

Production Surfaces

Production Start

Survey surface from the opening date

Production End

Survey surface from the closing date

Schedule Surfaces

Schedule Start

Plan depletion surface from the opening date

Schedule End

Plan depletion surface from the closing date

Schedule Future

(Optional) Plan depletion surface for the next time period

Multiple surface sets can be created having different start and end surfaces. Surface sets are then applied to defined regions in the following "Polygons" step.

The Schedule Future surface may be used to differentiate between "Over Dig" and "Out of Plan" material. See SC. Domain Mappings for more information.