Gantt labels may be configured in Schedule tab > Gantt tab > top left dropdown > Configure Global Display Options.

Steps to create a custom blast label.

To organise Gantt labels:

  1. Select ‘Configure Global Display Options’ from the view switcher.

  2. Add four labels to the Labels tab:

    1. Label Above

    2. Label Inside

    3. Label Below

    4. Tooltip

  3. In the Label Above group, choose what to show above delays, blasts, drills, stockpiles, and so on (for example: hours, kilograms, meters, and tonnes).

    1. Repeat for Label Inside, Label Below, and Tooltip.

Press the gear icon to add custom labels, such as multi-line tooltips or concatenated labels.