Overview
Allows users to specify which blocks should be mined by which period.
Maps end-of-period surfaces against blocks, assigning periods to blocks that are above an end-of-period surface.
Configure how strongly the schedule should adhere to these in the Schedule > Calendar tab > Guidance rows.
Enabling Guidance
Configuring Guidance Sets
Guidance Sets are collections of EOP surfaces. These are largely for organisational purposes only - all EOP surfaces are combined into a single collection when target periods are being assigned to blocks.
Records panel and Viewport
In the Records panel, select the levels/records or Record Subsets you want to display in the Viewport.
Navigating through the viewport and the tree structure of the records is the same as in other steps. For more information, see UI. Tree Structure and Viewport.
Layers panel
The Layers panel is used to import and display any relevant surfaces and solids. For more information, see in the section UI. Layers/Overlays panel.
Data panel
Data panel is used to review mining properties of the selected records. For more information, see in the section UI. Data panel.
To hide any one or several of these panels, use the pin icon provided in the upper right corner of each panel.
Note that you don’t see any updated guidance-based data in this setup step. The software calculates what period each reserve block should be mined by only when moving to the next setup item.
Calendar Inputs
Calendar inputs allow users to control how much influence end of period surfaces have on the schedule.
Guidance
To configure and review guidance impact on the schedule outcome, navigate to the Schedule > Calendar tab > Guidance rows. See the explanation below.
Period Matching Incentive | Schedule will focus on matching each individual period. Higher values will mean that blocks assigned a period to be mined will be given a higher priority, provided that the targeted period has not already been reached. |
Period Match Lookahead | How many future periods impact the schedule. Blocks with assigned periods later than this many periods relative to the current period will be ignored. The closer the current period is to the block’s targeted period, the higher the incentive applied against the block. |
Delayed Block Incentive | Schedule will increase the incentive on blocks that are behind plan. The more periods have passed between the block’s target period and the current period, the stronger the incentive. |
Agents
Navigate to the Agents section to set the Strategic Guidance Weight for each Agent.
Strategic Guidance Weight | How strongly each agent will follow the guidance. |
0 Comments