SC. Domain Mappings


Spatial Conformetrics looks at the intersection of a production solid and a schedule solid generated from a set of start and end surfaces. The resultant solids are then divided up into various domain solids based on how they interact with one another.

The cross-sectional diagram below visually depicts the conformance domains based on the two solids intersecting.


Types of Domains

Domain Name

Solid Type

Description

Cut Out of Plan

Production

Represents mined material that was not scheduled to be mined. The production solid does not overlap with the scheduled solid.

Cut Late

Production

Represents mined material that was sitting above planned material. The production solid does not overlap with the scheduled solid.

Over Cut

Production

Represents mined material that is below planned material. The production solid does not overlap with the scheduled solid.

Not Cut

Scheduled

Represents planned material that was not mined. The scheduled solid does not overlap with the production solid.

Cut Early

Scheduled

Represents planned material that was mined prior to the start date. The scheduled solid does not overlap with the production solid.

Under Cut

Scheduled

Represents planned material that was not fully mined. The scheduled solid does not overlap with the production solid.

Cut in Plan

Both

Represents planned material that was mined. The scheduled solid does overlap with the production solid.

Domains types

In the example above:

  • Any intersecting volume is "Cut in Plan".

  • Any production volume outside the schedule boundary is "Cut Out of Plan".

  • Any schedule volume outside the production boundary is " Not Cut".

  • Any production volume above or below a schedule solid is "Cut Late" or "Over Cut".

  • Any schedule volume above or below a production solid is "Cut Early" or "Under Cut".

Domain Configuration

Different organizations may choose to report these domains with different names or combine them. This can be achieved by editing the domains “Reporting Name”. Other domain settings are located in the table directly below.

Column

Description

 

Column

Description

 

Reporting Name

The name which will be used for reporting purposes.

Cut or Fill

Is the domain a cut solid (mining) or a fill solid (dumping).

Solid Type

The parent solid of the domain, i.e - Scheduled, Production, Both.

Compliant

Whether or not the domain is ‘compliant’. Will be used for the Plan Compliance (Compliant / Scheduled) reporting result.

Color

Color which will visually represent the domain solid.