PS. Period Plot Report


The Period Plots report is used to present 2D graphical plots of the selected activities in a given time period.

What’s new

In APS versions 22.2 and newer, the functionality to create Period Plots has been moved into the Reports tab. Therefore, the Period Plot tab in the Schedule no longer present. In addition, several new configuration options have been added, including the ability only to show benches that have been scheduled and the ability to view the benches in a List form rather than a Tree form.

Period Plots reports moved to Reporting tab

Setup

To create a plot, add a new Period Plot report and populate the applicable settings, as explained below.

Note that Period Plots folder is added to your reports list by default.

You can create several plots for different activities, such as Drilling, Charging, Blasting and Mining.

In the Setup tab, set the display parameters for the different components.

Plot Setup items are explained in the table below:

Settings

Main settings of the plot content.

Activity

Select the Activity type to report, it can be “ProductionDrilling”, “ProductionCharging”, “Mining” or “ProductionBlasting” (or other, if set in the Production Mode Features step).

Label

Use the Labels dropdown to select which labels you want to display on the plot (for example, drilling meters for the ProductionDrilling activity or wet_tonnes for Mining). The default setting is <Record Name>.

Period Subset

Select what Period Subset to show. The available subsets are configured in the Period Subsets step. The default setting is <All Periods>.

Show Scale

Select how to display a scale for the plot ("Scale", "Grid", "None").

Expand Distance (m)

Optionally specify Expand Distance, in meters.

Draw Layers Over Blocks

Flag this option, if you want to draw layers over blocks. Note, that only polyline layers can be displayed.

Display Increment As

Select how you want to display benches/lifts, in a Tree form or in a List form.

Show Only Scheduled Increments

Flag this option, if you want to display in the tree/list of benches only those that are scheduled in your plan. The increments that are not being worked on during the specified time period will not be included in the list.

Shading Opacity

Specify a preferred Shading Opacity, from 0.1 to 1.

Scheduled Hatch Pattern

Select from the dropdown a preferred Hatch Pattern for the Scheduled Blocks. For better illustration, “Solid” type is recommended.

Already Done Text

Text for already done (already drilled/charged/mined) blocks, that will be shown in the Legend. The default text is <Already Done>.

Already Done Hatch Pattern

Hatch Pattern of already done blocks.

Already Done Color

Color of already done blocks.

Period

Periods display settings.

Min Period

Select from the dropdown Minimum period to show in the plot. The default selection is <Start of Schedule>.

Max Period

Select from the dropdown Maximum period to show in the plot. The default selection is <End of Schedule>.

Title

Title display settings.

Show Title

Flag to show a selected level Title at the top.

Font

Title font selection.

Size

Title size selection.

Style

Title style selection.

Labels

Labels display settings.

Show Labels

Flag to show a block property (i.e. blast type) over every block.

Font

Label font selection.

Size

Label size selection.

Style

Label style selection.

Show Labels only for Scheduled Blocks

Flag to show labels only for scheduled blocks.

Legends

Legend display settings.

Show Legends

If Show Legends is ticked, you will see a legend of color assignments by period on the right side of the viewport.

Font

Legend font selection.

Size

Legend size selection.

Style

Legend style selection.

Show Used Periods Only

Flag to show used periods only.

Image Size

Exported image settings.

Width

Enter the width of the plot.

Height

Enter the height of the plot.

Results

Select a bench/flitch or lift from the tree/list on the left and its blocks will be displayed in the main viewport.

Use the <CTRL> and <SHIFT> keys to select multiple levels from the tree structure on the left.

Note that it is not possible to display the level of the entire pit or stage, the selection may only contain benches, flitches and lifts.

Saving Results

You can save and export the displayed plot directly from the viewport by right-clicking and selecting "Save" from the dropdown.

  • In the Save As window specify saving path, name and format of the plot being exported, and click Save.

  • Open the saved file to review results.