SC. Domain Mappings
Overview
Spatial Conformetrics looks at the intersection of a production solid and a schedule solid generated from a set of start and end surfaces. The resultant solids are then divided up into various domain solids based on how they interact with one another.
The cross-sectional diagram below visually depicts the conformance domains based on the two solids intersecting.
Types of Domains
Domain Name | Solid Type | Description |
Cut Out of Plan | Production | Represents mined material that was not scheduled to be mined. The production solid does not overlap with the scheduled solid. |
Cut Late | Production | Represents mined material that was sitting above planned material. The production solid does not overlap with the scheduled solid. |
Over Cut | Production | Represents mined material that is below planned material. The production solid does not overlap with the scheduled solid. |
Not Cut | Scheduled | Represents planned material that was not mined. The scheduled solid does not overlap with the production solid. |
Cut Early | Scheduled | Represents planned material that was mined prior to the start date. The scheduled solid does not overlap with the production solid. |
Under Cut | Scheduled | Represents planned material that was not fully mined. The scheduled solid does not overlap with the production solid. |
Cut in Plan | Both | Represents planned material that was mined. The scheduled solid does overlap with the production solid. |
In the example above:
Any intersecting volume is "Cut in Plan".
Any production volume outside the schedule boundary is "Cut Out of Plan".
Any schedule volume outside the production boundary is " Not Cut".
Any production volume above or below a schedule solid is "Cut Late" or "Over Cut".
Any schedule volume above or below a production solid is "Cut Early" or "Under Cut".
Domain Configuration
Different organizations may choose to report these domains with different names or combine them. This can be achieved by editing the domains “Reporting Name”. Other domain settings are located in the table directly below.
Column | Description |
|
---|---|---|
Reporting Name | The name which will be used for reporting purposes. | |
Cut or Fill | Is the domain a cut solid (mining) or a fill solid (dumping). | |
Solid Type | The parent solid of the domain, i.e - Scheduled, Production, Both. | |
Compliant | Whether or not the domain is ‘compliant’. Will be used for the Plan Compliance (Compliant / Scheduled) reporting result. | |
Color | Color which will visually represent the domain solid. |